The correct sequence of operations in production planning and control is

ARouting-Scheduling-Dispatching-Follow up

BScheduling-Routing- Dispatching-Follow up

CDispatching-Routing-Scheduling- Follow up

DRouting-Scheduling-Follow up-Dispatching

Answer:

A. Routing-Scheduling-Dispatching-Follow up

Read Explanation:

Routing-Scheduling-Dispatching-Follow up