The efficiency of A, B, and C is 2 : 3 : 5. A alone can complete a work in 50 days. They all work together for 5 days and then C left the work, in how many days A and B together can complete the remaining work?

A50 days

B30 days

C20 days

D10 days

Answer:

D. 10 days

Read Explanation:

Total work = Efficiency × Time Let efficiency of A be 2 units/day Efficiency of A, B and C = 2 : 3 : 5 Total work = 2 × 50 = 100 units Work done by A, B and C in 5 days = (2 + 3 + 5) × 5 = 10 × 5 = 50 units Remaining work = 100 – 50 = 50 units ∴ Time taken by A and B to complete the remaining work = 50/(2 + 3) = 50/5 = 10 days


Related Questions:

A and B can complete a piece of work in 10 days and 12 days, respectively. If they work on alternate days beginning with A, then in how many days will the work be completed?
A, B and C contract to do a work for Rs. 4200. A can do the work in 6 days, B in 10 days and C in 12 days. If they work together to do the work, what is the share of C (in Rs.)?
Sita is twice efficient than Gita. If together they complete the work in 15 days. Find the difference of number of days between Gita and Sita.
A fort is provisioned for 32 days for some soldiers. After 4 days, a reinforcement of 150 soldiers arrived and the food will now last for 21 days only. How many soldiers were there in the fort in the beginning?
A and B together can complete a piece of work in 12 days, B and C can do it in 20 days and C & A can do it in 15 days. A, B and C together can complete it in.