The working efficiency of Raja, Ram and Mohan is 6 : 3 : 2. Raja can complete the whole work in 10 days. Raja and Ram together work for the first two days and then Raja and Mohan work for next 4 days and the remaining work is completed by Mohan. Find the total time taken to complete the work.

A11 days

B5 days

C6 days

D10 days

Answer:

A. 11 days

Read Explanation:

Solution: Given: The working efficiency of Raja, Ram and Mohan is 6 : 3 : 2. Raja can complete the whole work in 10 days. Raja and Ram together work for the first two days. Raja and Mohan work for next 4 days. The remaining work is completed by Mohan. Formula used: Work = Efficiency × Time Calculation: The working efficiency of Raja = 6k The working efficiency of Ram = 3k The working efficiency of Mohan = 2k Let k = 1, The working efficiency of Raja = 6 units per day The working efficiency of Ram = 3 units per day The working efficiency of Mohan = 2 units per day The total amount of work or the amount of work done by Raja in 10 days = 6 × 10 = 60 units Now, The combined efficiency of Raja and Ram = 6 + 3 = 9 units a day The total work done by Raja and Ram in first 2 days = 9 × 2 = 18 units Now, The combined efficiency of Raja and Mohan = 6 + 2 = 8 units a day The total work done by Raja and Mohan in next 4 days = 8 × 4 = 32 units The remaining work = 60 - 18 - 32 = 10 units Now, The time is taken by Mohan to complete the remaining work = 102 = 5 days The total time is taken complete the work = 2 + 4 + 5 = 11 days ∴ The total time is taken to complete the work is 11 days.


Related Questions:

6 പേർ 12 ദിവസം കൊണ്ട് ഒരു ജോലി പൂർത്തിയാക്കുന്നു. എങ്കിൽ 8 പേർ എത്ര ദിവസംകൊണ്ട് ആ ജോലി പൂർത്തീകരിക്കും ?
A man running at a speed of 15 km/hr crosses a bridge in 3 minutes. What is the length of the bridge?
Sankar and Vishnu work alternately in a tailoring shop on an order of stitching 21 suits. Sankar starts the work, stitches 3 suits in two days, and takes a break, during which Vishnu stitches 3 suits in three days, and then takes a break. This pattern is repeated till all the 21 suits are stitched. How many days did it take the duo to complete the work?
A alone can complete the project in 10 days; B alone can complete it in 20 days while C alone can complete it in 30 days. They together earn Rs. 1,100 for the project. By how much do the total earnings of A and C exceed the earnings of B?
Six typists can type a given data in 16 days. How many days will 4 typists take to do the same work?