App Logo

No.1 PSC Learning App

1M+ Downloads
Two men and 7 women can complete a work in 28 days, whereas 6 men and 16 women can do the same work in 11 days. In how many days will 5 men and 4 women, working together, complete the same work?

A22

B18

C14

D20

Answer:

A. 22

Read Explanation:

Solution: Given: 2 men and 7 women can complete a work in 28 days 6 men and 16 women can do the same work in 11 days Concept used: Work = Total manpower × Total days M1D1/W1 = M2D2/W2 Calculation: Let the efficiency of 1 man be M. And the efficiency of 1 woman is W. According to the question, 2 men and 7 women complete a work in 28 days = 6 men and 16 women complete the same work in 11 days ⇒ (2M + 7W) × 28 = (6M + 16W) × 11 ⇒ 56M + 196W = 66M + 176W ⇒ 10M = 20W ⇒ M = 2W 2 men and 7 women = 2M + 7W ⇒ 2 men and 7 women = 4W + 7W ⇒ 2 men and 7 women = 11W 5 men and 4 women = 5M + 4W ⇒ 5 men and 4 women = 10W + 4W ⇒ 5 men and 4 women = 14W M1D1/W1 = M2D2/W2 ⇒ 11W × 28 = 14W × D2 ⇒ D2 = 22 days ∴ 5 men and 4 women, working together, complete the same work in 22 days.


Related Questions:

15 men finish a job in 21 days by working 8 hour a day. If 3 women work equal to 2 men, then how many days will 21 women take to complete the work by working 6 hours/day?
Midhun writes the numbers 1 to 100. How many times does he write the digit'0' ?
നാല് പേർ ചേർന്ന് ഒമ്പത് ദിവസം കൊണ്ട് തീർക്കുന്ന ഒരു ജോലി ആറ് ദിവസം കൊണ്ട്തീർക്കണമെങ്കിൽ എത്ര ജോലിക്കാരെ കൂടി കൂടുതലായി വേണ്ടിവരും ?
ഒരു ജോലി പൂർത്തിയാക്കാൻ രാജന് 6 ദിവസവും ബിനുവിന് 12 ദിവസവും വേണം. എങ്കിൽ രണ്ടു പേരും കൂടി ഈ ജോലി എത്ര ദിവസം കൊണ്ട് പൂർത്തിയാക്കും?
In a box there are 16 white socks and 12 black socks. A person picked socks with closed eye. The minimum number of socks that he has to pick to get a pair?