App Logo

No.1 PSC Learning App

1M+ Downloads
Two men and 7 women can complete a work in 28 days, whereas 6 men and 16 women can do the same work in 11 days. In how many days will 5 men and 4 women, working together, complete the same work?

A22

B18

C14

D20

Answer:

A. 22

Read Explanation:

Solution: Given: 2 men and 7 women can complete a work in 28 days 6 men and 16 women can do the same work in 11 days Concept used: Work = Total manpower × Total days M1D1/W1 = M2D2/W2 Calculation: Let the efficiency of 1 man be M. And the efficiency of 1 woman is W. According to the question, 2 men and 7 women complete a work in 28 days = 6 men and 16 women complete the same work in 11 days ⇒ (2M + 7W) × 28 = (6M + 16W) × 11 ⇒ 56M + 196W = 66M + 176W ⇒ 10M = 20W ⇒ M = 2W 2 men and 7 women = 2M + 7W ⇒ 2 men and 7 women = 4W + 7W ⇒ 2 men and 7 women = 11W 5 men and 4 women = 5M + 4W ⇒ 5 men and 4 women = 10W + 4W ⇒ 5 men and 4 women = 14W M1D1/W1 = M2D2/W2 ⇒ 11W × 28 = 14W × D2 ⇒ D2 = 22 days ∴ 5 men and 4 women, working together, complete the same work in 22 days.


Related Questions:

Pravin can do a piece of work in 6 hours. Rishi can do it in 28 hours. With the assistance of Shan, they completed the work in 4 hours. In how many hours can Shan alone do it?
ഒരു ജോലി ചെയ്ത് തീർക്കാൻ 16 പേർക്ക് 30 ദിവസം വേണം. എന്നാൽ 20 ദിവസം കൊണ്ട് പൂർത്തിയാക്കാൻ എത്ര പേരെ കൂടുതൽ നിയമിക്കണം?
24 people can finish a job by 10 days. How many days will be required to finish the same job by 8 people?
Two pipes A and B can fill a tank in 15 and 30 minutes respectively. If both the pipes are used together, then how long will it take to fill the tank ?
A യും B യും C യും കൂടി ഒരു ജോലി 4 ദിവസം കൊണ്ടു ചെയ്തുതീർക്കുന്നു. A തനിയെ 12 ദിവസം കൊണ്ടും B തനിയെ 18 ദിവസം കൊണ്ടും ചെയ്തുതീർത്താൽ C യ്ക്ക് തനിയെ ആ ജോലി ചെയ്യാൻ വേണ്ടി വരുന്ന ദിവസമെത്ര?