App Logo

No.1 PSC Learning App

1M+ Downloads
Vijayan can do a job in 25 days and Achyuth can do it in 20 days. Vijayan started the work and Achyuth joined af. ter 15 days and Vijayan left. How many days did Achyuth take to complete the ramaining job?

A16

B15

C17

D8

Answer:

D. 8

Read Explanation:

Total work can be taken as LCM of 25, 20 ie equal to 100 Efficiency of Vijayan 100/25 = 4 Efficiency of Achyuth = 100/20 = 5 Work done be Vijayan in 15 days = 15 x 4 = 60 Balance work = 100 - 60 = 40 No. of days to complete 40 works by Achyuth = 40/5 = 8 days


Related Questions:

'A' can do a piece of work in 10 days. He works at it for 8 days and then B finished the work in 16 days. How long will they take to complete the work if they do it together?
Isha can do a certain piece of work in 15 days. Isha and Smriti can together do the same work in 11 days, and Isha, Smriti and Ashlesha can do the same work together in 10days. In how many days can Isha and Ashlesha do the same work?
45 ആൾക്കാർ ഒരു ദിവസം 12 മണിക്കൂർ ജോലി ചെയ്ത് 30 ദിവസം കൊണ്ട് ഒരു ജോലി പൂർത്തിയാക്കുമെങ്കിൽ 60 ആൾക്കാർ ഒരു ദിവസം പത്തു മണിക്കൂർ വീതം ജോലി ചെയ്താൽ എത്ര ദിവസം കൊണ്ട് ജോലി പൂർത്തിയാക്കും?
A alone can complete a work in 14 days and B alone can complete the same work in 21 days. A and B start the work together but A leaves the work after 4 days of the starting of work. In how many days B will complete the remaining work?
ഒരു ജോലി A-യ്ക്ക് 5 ദിവസം കൊണ്ടും B-യ്ക്ക് 20 ദിവസം കൊണ്ടും തീർക്കാൻ കഴിയും. അതേ ജോലി A-യും B-യുംകൂടി ഒരുമിച്ച് ചെയ്താൽ എത ദിവസംകൊണ്ട് തീർക്കാൻ കഴിയും?