App Logo

No.1 PSC Learning App

1M+ Downloads
Vijayan can do a job in 25 days and Achyuth can do it in 20 days. Vijayan started the work and Achyuth joined af. ter 15 days and Vijayan left. How many days did Achyuth take to complete the ramaining job?

A16

B15

C17

D8

Answer:

D. 8

Read Explanation:

Total work can be taken as LCM of 25, 20 ie equal to 100 Efficiency of Vijayan 100/25 = 4 Efficiency of Achyuth = 100/20 = 5 Work done be Vijayan in 15 days = 15 x 4 = 60 Balance work = 100 - 60 = 40 No. of days to complete 40 works by Achyuth = 40/5 = 8 days


Related Questions:

15 സ്ത്രീകൾക്ക് 18 ദിവസം കൊണ്ട് ഒരു ജോലി ചെയ്യാം. 27 ദിവസം കൊണ്ട് ജോലി പൂർത്തിയാക്കാൻ എത്ര സ്ത്രീകൾ വേണം?
Nitin can do a piece of work in 7 hours. Pravin can do it in 21 hours. With the assistance of Rishi, they completed the work in 3 hours. In how many hours can Rishi alone do it?
If P and Q together can do a job in 15 days, Q and R together can do it in 12 days and P and R together can do the same in 20 days, then in how many days will the job be completed, if all the three work together?
എ ബി സി എന്നിവയ്ക്ക് യഥാക്രമം 20 30 60 ദിവസങ്ങളിൽ ഒരു ജോലി ചെയ്യാൻ കഴിയും ഓരോ മൂന്നാം ദിവസവും ബി ,സി എന്നിവർ സഹായിച്ചാൽ എ ക്ക് എത്ര ദിവസത്തിനുള്ളിൽ ജോലി പൂർത്തിയാക്കാൻ കഴിയും
Two pipes A and B can seperately fill a cistern in 60 min. and 75 min. respectively. There is a third pipe in the bottom of cistern to empty it. If all the three pipes are simultaneously opened, then the cistern is full in 50 min. In how much time third pipe alone can empty the cistern.