Which one of the following scheduling measures is not related to due date or delivery time?

AFlow time

BTardiness

Clateness

DNumber of tardy jobs

Answer:

A. Flow time

Read Explanation:

Flow time is the total time a job spends in the production system from arrival to completion, and it is not directly related to the due date or delivery time. Tardiness, lateness, and the number of tardy jobs are all measures that relate to how well the schedule meets the due dates.