While doing the project planning of a Construction: project, using PERT, it is intended to identify the variance of the project. This can be done by:

ASum of variance of the activities along critical path of the project

BSum of squares of the total floats of all activities in the project

CSum of squares of free floats of all activities along the critical path of the in the project.

DSum of variance of all activities of the project

Answer:

A. Sum of variance of the activities along critical path of the project

Read Explanation:

In PERT, the project variance is calculated by summing the variances of the activities that lie on the critical path. The activities on the critical path are the ones that, if delayed, would delay the entire project. Therefore, understanding the variance along this path can give an indication of the potential variation in the project's duration.


Related Questions:

One of the assumptions in the game theory is:
Monte Carlo simulation of queues is used when
______________ may be defined as any adjustment to the arrow diagram which becomes necessary owing to departure from the project schedule laid down earlier.
In queuing theory, the ratio of the mean arrival rate and the mean service rate is called the-
In network techniques, PERT stands for: