While doing the project planning of a Construction: project, using PERT, it is intended to identify the variance of the project. This can be done by:

ASum of variance of the activities along critical path of the project

BSum of squares of the total floats of all activities in the project

CSum of squares of free floats of all activities along the critical path of the in the project.

DSum of variance of all activities of the project

Answer:

A. Sum of variance of the activities along critical path of the project

Read Explanation:

In PERT, the project variance is calculated by summing the variances of the activities that lie on the critical path. The activities on the critical path are the ones that, if delayed, would delay the entire project. Therefore, understanding the variance along this path can give an indication of the potential variation in the project's duration.


Related Questions:

A variable that has no physical meaning, but is used to obtain an initial basic feasible solution to the linear programming problem is referred to as:
The amount of time by which an activity can be delayed without affecting project completion time is
As per one of the assumptions of linear programming problem in operation research, objective function and constraints are assumed to be _____________
Monte Carlo simulation of queues is used when
In a transportation problem North-West corner rule would yield :