While doing the project planning of a Construction: project, using PERT, it is intended to identify the variance of the project. This can be done by:
ASum of variance of the activities along critical path of the project
BSum of squares of the total floats of all activities in the project
CSum of squares of free floats of all activities along the critical path of the in the project.
DSum of variance of all activities of the project