The amount of time by which an activity can be delayed without affecting project completion time is

AFree float

BTotal float

CIndependent float

DActivity float

Answer:

B. Total float

Read Explanation:

The amount of time by which an activity can be delayed without affecting the project completion time is called total float.


Related Questions:

Any linear programming model must have all of the following properties EXCEPT:
In industrial engineering application PERT has

Consider the following statements regarding project management:Which of the given statements are INCORRECT?

  1. PERT is probabilistic and CPM is deterministic.
  2. In PERT, network slack on various events is calculated,
  3. In PERT, activity duration is normally distributed and project duration is beta distributed.
  4. The critical path of a network is the path that takes the shortest time.
    Slack represents the difference between the-
    In PERT analysis, the possible number of time estimates for activities linking up two events are -