Work study is mainly aimed at

ADetermining the most efficient method of performing a job

BEstablishing the minimum time of completion of job

CDeveloping the standard method and standard time of a job

DEconomizing the motions involved on the part of the worker while performing a job.

Answer:

C. Developing the standard method and standard time of a job

Read Explanation:

Work study is a technique used to improve productivity by analyzing the methods of carrying out an activity, setting up standards of performance, and determining the standard time for performing a job. It involves method study (motion study) and time study (work measurement) to simplify a job, reduce excess work, and wasteful use of resources. The main aim of work study is to develop the standard method and standard time of a job.


Related Questions:

Method study is
Which of the following is referred to as MRP II?
During manufacture of cement, the handling of lime stone

If an object is being painted while transported by chain conveyor can be shown by symbol

image.png
A technique of Work measurement in which times established for basic human motions are used to build up the time for a job at the defined level of performance is called: