______________ may be defined as any adjustment to the arrow diagram which becomes necessary owing to departure from the project schedule laid down earlier.

AOptimum cost

BNetwork updating

CArrow diagram

DOptimum time

Answer:

B. Network updating

Read Explanation:

Network updating refers to adjustments made to the arrow diagram due to deviation from the original project schedule. This is not related to optimum cost or optimum time.


Related Questions:

The first and last activities of a network diagram

Consider the following statements regarding linear programming:Which of the given statements are correct?

  1. The graphical method cannot solve a linear programming problem with three variables and two constraints.
  2. In the Big-M method, when the artificial variable leaves the basis, its column can be deleted from the subsequent tables.
  3. When one constraint line comes parallel to the objective function line, LPP will have a degenerate solution.
    In PERT analysis, a critical activity has:
    In a transportation problem North-West corner rule would yield :
    The primary objective of crashing in CPM is