______________ may be defined as any adjustment to the arrow diagram which becomes necessary owing to departure from the project schedule laid down earlier.
AOptimum cost
BNetwork updating
CArrow diagram
DOptimum time
AOptimum cost
BNetwork updating
CArrow diagram
DOptimum time