Challenger App

No.1 PSC Learning App

1M+ Downloads
In industrial engineering application PERT has

Afour time estimate

Bone time estimate

Cthree time estimate

Dtwo time estimate

Answer:

C. three time estimate

Read Explanation:

PERT is a project management technique similar to CPM. It assumes that each activity duration follows a statistical distribution. PERT uses three time estimates for each activity, namely optimistic, most likely and pessimistic time. The beta distribution is used to represent activity durations, which can be skewed towards the high or low end of the data range. The project duration is represented by a normal distribution, which is the sum of weighted averages of activities on the critical path.


Related Questions:

Which of the following artificial activity suggests that an activity following it cannot happen unless, the previous activity is completed?

Consider the following statements regarding project management:Which of the given statements are INCORRECT?

  1. PERT is probabilistic and CPM is deterministic.
  2. In PERT, network slack on various events is calculated,
  3. In PERT, activity duration is normally distributed and project duration is beta distributed.
  4. The critical path of a network is the path that takes the shortest time.
    Monte Carlo simulation of queues is used when
    Customers waiting at a barber shop is an example of queuing model.
    One of the assumptions in the game theory is: