App Logo

No.1 PSC Learning App

1M+ Downloads
In industrial engineering application PERT has

Afour time estimate

Bone time estimate

Cthree time estimate

Dtwo time estimate

Answer:

C. three time estimate

Read Explanation:

PERT is a project management technique similar to CPM. It assumes that each activity duration follows a statistical distribution. PERT uses three time estimates for each activity, namely optimistic, most likely and pessimistic time. The beta distribution is used to represent activity durations, which can be skewed towards the high or low end of the data range. The project duration is represented by a normal distribution, which is the sum of weighted averages of activities on the critical path.


Related Questions:

Which of the following statements is FALSE about CPM?
In PERT analysis, the possible number of time estimates for activities linking up two events are -
In linear programming problem when does feasibility change?
In a network diagram, an activity having a dotted arrow between activities is often referred to as a/an __________________ activity.

Consider the following statements in respect of PERT and CPM: Which of the statements are correct?

  1. PERT is event-oriented while CPM is activity-oriented.
  2. PERT is probabilistic while CPM is deterministic.
  3. Levelling and smoothing are the techniques related to resource scheduling in CPM.