App Logo

No.1 PSC Learning App

1M+ Downloads
10 men can finish a piece of work in 10 days, whereas it takes 12 women to finish it in 10 days. If 15 men and 6 women undertake to complete the work, how many days will they take to complete it ?

A2

B4

C5

D11

Answer:

C. 5

Read Explanation:

Solution: Given: 10 men can finish a piece of work in 10 days, whereas it takes 12 women to finish it in 10 days. Concept Used: Total Men × Day = Total Work Men × Days = Women × Days Calculation: 10 men can finish a piece of work in 10 days, whereas it takes 12 women to finish it in 10 days. ⇒ 10 M × 10 = 12 W × 10 ⇒ M/W = 6/5 Total Work = 10 × 6 × 10 ⇒ 600 If 15 men and 6 women undertake to complete the work ⇒ 600/(15 × 6 + 6 × 5) ⇒ 600/(120) ⇒ 5 Days ∴ 5 days will they take to complete it.


Related Questions:

Prakash and Vinesh can complete a certain piece of work in 10 and 8 days, respectively, They started to work together, and after 3 days, Vinesh left. In how many days will Prakash complete the remaining work?
A and B can do a piece of work in 10 days and 15 days, respectively. They work together for 4 days. The remaining work is completed by C alone in 12 days. C alone will complete 4/9 part of the original work in:
If 16 men or 28 women can do a work in 40 days. How long 24 men and 14 women will take to complete the work ?
Thirty men can complete a work in 36 days. In how many days can 18 men complete the same piece of work?
A,B യുടെ ഇരട്ടി വേഗത്തിൽ ജോലി ചെയ്യും. B 36 ദിവസം കൊണ്ട് ജോലി ചെയ്തു തീർക്കും എങ്കിൽ രണ്ടു പേരും കൂടി എത്ര ദിവസം കൊണ്ട് ആ ജോലി ചെയ്തു തീർക്കും?