10 men can finish a piece of work in 10 days, whereas it takes 12 women to finish it in 10 days. If 15 men and 6 women undertake to complete the work, how many days will they take to complete it ?
A2
B4
C5
D11
Answer:
C. 5
Read Explanation:
Solution:
Given:
10 men can finish a piece of work in 10 days, whereas it takes 12 women to finish it in 10 days.
Concept Used:
Total Men × Day = Total Work
Men × Days = Women × Days
Calculation:
10 men can finish a piece of work in 10 days, whereas it takes 12 women to finish it in 10 days.
⇒ 10 M × 10 = 12 W × 10
⇒ M/W = 6/5
Total Work = 10 × 6 × 10
⇒ 600
If 15 men and 6 women undertake to complete the work
⇒ 600/(15 × 6 + 6 × 5)
⇒ 600/(120)
⇒ 5 Days
∴ 5 days will they take to complete it.