App Logo

No.1 PSC Learning App

1M+ Downloads
10 men can finish a piece of work in 10 days, whereas it takes 12 women to finish it in 10 days. If 15 men and 6 women undertake to complete the work, how many days will they take to complete it ?

A2

B4

C5

D11

Answer:

C. 5

Read Explanation:

Solution: Given: 10 men can finish a piece of work in 10 days, whereas it takes 12 women to finish it in 10 days. Concept Used: Total Men × Day = Total Work Men × Days = Women × Days Calculation: 10 men can finish a piece of work in 10 days, whereas it takes 12 women to finish it in 10 days. ⇒ 10 M × 10 = 12 W × 10 ⇒ M/W = 6/5 Total Work = 10 × 6 × 10 ⇒ 600 If 15 men and 6 women undertake to complete the work ⇒ 600/(15 × 6 + 6 × 5) ⇒ 600/(120) ⇒ 5 Days ∴ 5 days will they take to complete it.


Related Questions:

If John can complete a job in 8 hours and Sara can complete the same job in 12 hours how long will it take them to complete the job together ?
40 mechanics can repair a bike in 56 days. In how many days 32 mechanics will do the same work?
Sankar and Vishnu work alternately in a tailoring shop on an order of stitching 21 suits. Sankar starts the work, stitches 3 suits in two days, and takes a break, during which Vishnu stitches 3 suits in three days, and then takes a break. This pattern is repeated till all the 21 suits are stitched. How many days did it take the duo to complete the work?
P and Q can do a work individually in 15 days and 20 days respectively. Find the respective ratio of their efficiencies.
Vikram and Vivek can finish a work in 50 days. They worked together for 20 days and then left. How much work has been done by them?