App Logo

No.1 PSC Learning App

1M+ Downloads
10 men can finish a piece of work in 10 days, whereas it takes 12 women to finish it in 10 days. If 15 men and 6 women undertake to complete the work, how many days will they take to complete it ?

A2

B4

C5

D11

Answer:

C. 5

Read Explanation:

Solution: Given: 10 men can finish a piece of work in 10 days, whereas it takes 12 women to finish it in 10 days. Concept Used: Total Men × Day = Total Work Men × Days = Women × Days Calculation: 10 men can finish a piece of work in 10 days, whereas it takes 12 women to finish it in 10 days. ⇒ 10 M × 10 = 12 W × 10 ⇒ M/W = 6/5 Total Work = 10 × 6 × 10 ⇒ 600 If 15 men and 6 women undertake to complete the work ⇒ 600/(15 × 6 + 6 × 5) ⇒ 600/(120) ⇒ 5 Days ∴ 5 days will they take to complete it.


Related Questions:

Vikram and Vivek can finish a work in 50 days. They worked together for 20 days and then left. How much work has been done by them?
20 buckets of water fill a tank when the capacity of each bucket is 13.5 litres. How many buckets will be required to fill the same tank ifthe capacity of each bucket is 9 litres?
Ramanan and Shyam together can do a work in 8 days. Both of B them began to work. After 3 days Ramanan fell ill, Shyam completed the remaining work in 15 days. In how many days can Ramanan complete the work?
20 buckets of water fill a tank when the capacity of each bucket is 13.5 litres. How many buckets will be required to fill the same tank if the capacity of each bucket is 9 litres?
A is twice as good as a workman as B. And together, they finish a piece of work in 20 days. In how many days, will A alone finish the work?