15 men can complete a task in 10 days. In how many days can 20 men complete the same task?5.5 days

A5.5 days

B7.5 days

C6.5 days

D8.5 days

Answer:

B. 7.5 days

Read Explanation:

Solution: Given: 15 men can complete a task in 10 days. Formula: M1 × D1 = M2 × D2 Calculation: M1 = 15, D1 = 10 and M2 = 20 According to the formual 15 × 10 = 20 × D2 ⇒ D2 = 150/20 ⇒ D2 = 7.5 days ∴ 20 men can complete the same task in 7.5 days.


Related Questions:

How many men will be required to plough 50 acres of land in 10 days if 15 men are required 6 days to plough 10 acres of land?
Thirty men take 20 days to complete a job working 9 hours a day. How many hour a day should 40 men take in 20 days to complete the job?
Raju can complete a work in 20 days, which Bobby, Arjun and Habib can finish Independently in 27, 30 and 36 days respectively, Raju and Arjan starts doing this work jointly and continues on it for 4 days and stops working. If one of Habib and Hobby has to complete the work, how many more days they may take respectively?
A യും B യും C യും കൂടി ഒരു ജോലി 4 ദിവസം കൊണ്ടു ചെയ്തുതീർക്കുന്നു. A തനിയെ 12 ദിവസം കൊണ്ടും B തനിയെ 18 ദിവസം കൊണ്ടും ചെയ്തുതീർത്താൽ C യ്ക്ക് തനിയെ ആ ജോലി ചെയ്യാൻ വേണ്ടി വരുന്ന ദിവസമെത്ര?
A pipe can filla tankin 30 minutes. Due to a leak in the bottom it is filled in 40 minutes. If the tank is full, how much time will the leak take to empty it?