Ravi, Manish and Naveen alone can complete a work in 30 days, 15 days and 10 days respectively. They start the work together but Ravi leaves the work after 2 days of the starting of the work and Manish leaves the work after 3 days more. In how many days Naveen will complete the remaining work?

A3

B4

C1

D2

Answer:

C. 1

Read Explanation:

Solution: Given: Ravi can complete the work 30 days Manish can complete it in 15 days And Naveen can complete it in 10 days Concept: In this type of question always imagine the total work as LCM of time taken by individuals to perform the work. Formula used: Efficiency = Total work/Time taken Calculation: Let the total work be LCM of 30, 15, 10 i.e. 30 unit So efficiency of Ravi = 30/30 = 1 unit/day Efficiency of Manish = 30/15 = 2 unit/day Efficiency of Naveen = 30/10 = 3 unit/day Ravi work for 2 days and performed work = 2 × 1 = 2 unit Manish work for 5 days and performed work = 5 × 2 = 10 unit Naveen 5 day work = 5 × 3 = 15 unit Remaining work = 30 – (2 + 10 + 15) = 3 unit ∴ Time taken by Naveen to complete the remaining work = 3/3 = 1 day


Related Questions:

A and B together complete a work in 8 days. If B is 25% more efficient than A, then in how many days will A alone complete the same work?
A can do a piece of work in 10 days and B in 20 days. They begin together but A leaves 2 days before the completion of the work. The whole work will be done in.
അജയൻ ഒരു ജോലി 2 മണിക്കുറും അരുൺ 6 മണിക്കൂറും ചെയ്തു. രണ്ട് പേർക്കും കൂടി ലഭിച്ച കൂലി 800 രൂപയാണ്. ഈ തുക എങ്ങനെയാണ് വീതിക്കേണ്ടത് ?
Pipes A, B and C can fill a tank in 15, 30 and 40 hours, respectively. Pipes A, B and C are opened at 6 a.m., 8 a.m. and 10 a.m., respectively, on the same day. When will the tank be full?
Two pipes A and B can fill a cistern in 3 hours and 5 hours respectively. Pipe C can empty in 2 hours. If all the three pipes are open, in how many hours the cistern will be full?