16 workers working 8 hours per day can demolish a building in 32 days. In how many days 24 workers working 12 hours per day can demolish the same building?

A128/3 days

B56/3 days

C128/9 days

D56/9 days

Answer:

C. 128/9 days

Read Explanation:

Solution: Given: 16 worker workers working 8 hours per day can demolish a building in 32 days. Formula used: (M × D × H)/W = constant Where, M = number of workers D = number of days H = number of hours W = work done Calculation: Let 24 workers working 12 hours per day can demolish the same building in x days According to formula, 16 × 8 × 32/(1) = 24 × 12 × x/(1) ⇒ 9x = 4 × 32 ⇒ x = 128/9 ∴ Number of days required to complete the work is 128/9 days.


Related Questions:

A tank can be filled by one tap in 2 hrs. and by another in 3 hrs. How long will it take if both taps are opened together ?
A യ്ക്ക് B യെക്കാൾ 75% ജോലി ചെയ്യാൻ കഴിയും.എന്നാൽ B ഒറ്റക്ക് 21 ദിവസംകൊണ്ട് ചെയ്യുന്ന ജോലി A യ്ക്ക് എത്ര ദിവസത്തിൽ പൂർത്തിയാക്കാൻ കഴിയും?
Two pipes are connected to a water tank. The first pipe can fill the tank in 10 minutes and the second pipe can empty it in 15 minutes. If both pipes opened simultaneously, then find the time in which the tank will be completely filled with water.
5 men and 8 women can complete a task in 34 days, whereas 4 men and 18 women can complete the same task in 28 days. In how many days can the same task be completed by 3 men and 5 women?
ഒരു ജോലി A-യ്ക്ക് 5 ദിവസം കൊണ്ടും B-യ്ക്ക് 20 ദിവസം കൊണ്ടും തീർക്കാൻ കഴിയും. അതേ ജോലി A-യും B-യുംകൂടി ഒരുമിച്ച് ചെയ്താൽ എത ദിവസംകൊണ്ട് തീർക്കാൻ കഴിയും?