16 workers working 8 hours per day can demolish a building in 32 days. In how many days 24 workers working 12 hours per day can demolish the same building?

A128/3 days

B56/3 days

C128/9 days

D56/9 days

Answer:

C. 128/9 days

Read Explanation:

Solution: Given: 16 worker workers working 8 hours per day can demolish a building in 32 days. Formula used: (M × D × H)/W = constant Where, M = number of workers D = number of days H = number of hours W = work done Calculation: Let 24 workers working 12 hours per day can demolish the same building in x days According to formula, 16 × 8 × 32/(1) = 24 × 12 × x/(1) ⇒ 9x = 4 × 32 ⇒ x = 128/9 ∴ Number of days required to complete the work is 128/9 days.


Related Questions:

A pipe can fill the tank in 10 minutes and another pipe can empty it in 12 minutes. If both the pipes are opened the time in which the tank is filled
A can do a piece of work in 12 days and B can do it in 18 days. They work together for 2 days and then A leaves. How long will B take to finish the remaining work ?
C alone can complete a work in 20 days and D alone can complete the same work in 30 days. In how many days C and D together can complete the same work?
15 പേർ 24 ദിവസം കൊണ്ട് ചെയ്ത് തീർക്കുന്ന ജോലി 18 ദിവസം കൊണ്ട് തീർക്കാൻ എത്ര പേർ വേണം?
Two pipes can fill a tank in 30 hours and 40 hours, respectively. Find the time (in hours) taken to fill the tank when both the pipes are opened simultaneously.