30 men working 5 hours a day can do a task in 16 days. In how many days will 40 men working 6 hours a day do the same task?

A12 days

B10 days

C15 days

D18 days

Answer:

B. 10 days

Read Explanation:

$$work done by them is equal,

${30men}\times{5hours}\times{16Days}={40Men}\times{6hours}\times{N Days}$

$N=\frac{{30}\times{5}\times{16}}{{40}\times{6}}$

$N =10 days$


Related Questions:

One pipe can fill the tank in 20 min while another pipe can empty it in 60 min. If both the pipes are operated together, how long will it take to fill the tank completely?
Two pipes can fill a cistern separately in 10 hours and 15 hours. They can together fill the cistern in
P, Q and R together do a piece of work for 535. P working alone can do it in 5 days. Q alone can do it in 6 days and R alone can do it in 7 days. Then what will be the share of R for its work.
A യും B യും ചേർന്ന് 12 ദിവസം കൊണ്ടും, A യും C യും ചേർന്ന് 8 ദിവസം കൊണ്ടും, B യും C യും ചേർന്ന് 6 ദിവസം കൊണ്ടും ഒരു ജോലി പൂർത്തിയാക്കാമെങ്കിൽ, B ഒറ്റയ്ക്ക് ആ ജോലി എത്ര ദിവസം കൊണ്ട് പൂർത്തിയാക്കും ?
One tap can fill a water tank in 40 minutes and another tap can make the filled tank empty in 60 minutes. If both the taps are open, in how many hours will the empty tank be filled ?