Given:
E alone can doi it in 30 days
In one day E alone can do it in 301 work
Calculation:
E1+F1=E+F1
F1=101−301
F1=302
F alone can do it in 230=15days.
Alternate Method:
E+F= 10 days
E =30 days
Efficiency of F = 3-1 = 2
F alone can do it in 230=15days.