Challenger App

No.1 PSC Learning App

1M+ Downloads
8 men can complete a piece of work in 8 days while 8 women can do it in 12 days. In how many days can 2 women and 4 men complete it?

A12 days

B8 days

C17 days

D16 days

Answer:

A. 12 days

Read Explanation:

Concept:

The amount of work done is proportional to the number of people, the rate at which they work, and the time they spend.

Work = Rate × Time × Number of People.

Men's Work Rate:

  • 8 men complete a work in 8 days.

  • This means 1 man's work rate is 1 / (8 men × 8 days) = 1/64 of the total work per day.

  • So, in one day, 1 man does 1/64 of the work.

Women's Work Rate:

  • 8 women complete the same work in 12 days.

  • This means 1 woman's work rate is 1 / (8 women × 12 days) = 1/96 of the total work per day.

  • So, in one day, 1 woman does 1/96 of the work.

Calculating Combined Work Rate

Combined Rate of 4 Men and 2 Women per Day:

  • The work done by 4 men in one day = 4 × (1/64) = 4/64 = 1/16 of the total work.

  • The work done by 2 women in one day = 2 × (1/96) = 2/96 = 1/48 of the total work.

  • The total work done by 4 men and 2 women in one day = (1/16) + (1/48).

  • To add these fractions, find a common denominator, which is 48.

  • (1/16) + (1/48) = (3/48) + (1/48) = 4/48 = 1/12 of the total work per day.

Determining the Time to Complete the Work

Calculation:

  • If 4 men and 2 women together complete 1/12 of the work in one day, they will complete the entire work (1 whole) in the reciprocal of this rate.

  • Time = Total Work / Combined Daily Rate

  • Time = 1 / (1/12) = 12 days


Related Questions:

A can finish painting a sari in 11 days, B in 20 days and C in 55 days, if they work independently. In how many days can the work be completed if A is assisted by B on every odd numbered day and by C on every even numbered day till the work completes?
108 കി.മി./മണിക്കൂർ വേഗത ______________ നു സമാനമാണ്
A can do a piece of work in 10 days. B can do it in 15 days. With the assistance of C, they completed the work in 2 days. C alone can do it in ______________days.
15 പേർക്ക് 16 ദിവസം കൊണ്ട് ഒരു ജോലി ചെയ്യാൻ കഴിയുമെങ്കിൽ. 4 ദിവസത്തിന് ശേഷം 3 പേർ കൂടി ജോലിയിൽ ചേർന്നു. ശേഷിക്കുന്ന ജോലി എത്ര ദിവസത്തിനുള്ളിൽ പൂർത്തിയാകും?
X ജോലിക്കാർക്ക് ഒരു ജോലി ചെയ്ത് തീർക്കാൻ 16 ദിവസം വേണം. എങ്കിൽ 2X ജോലിക്കാർക്ക് അതിന്റെ പകുതി ജോലി ചെയ്തു തീർക്കാൻ ആവശ്യമായ ദിവസം കണക്കാക്കുക.