If 200 men can dig a canal working for 8 hours a day in 6 days, how long will it take to dig the canal, if 300 men work 6 hours per day?
A$6 \,days$
B$5\frac{1}{3}\,days$
C$4\frac{2}{3}\,days$
D$7\,days$
A$6 \,days$
B$5\frac{1}{3}\,days$
C$4\frac{2}{3}\,days$
D$7\,days$