If 200 men can dig a canal working for 8 hours a day in 6 days, how long will it take to dig the canal, if 300 men work 6 hours per day?

A6 days

B$$5\frac13$ days$

C$$4\frac23$days$

D7days

Answer:

$$5\frac13$ days$

Read Explanation:

Step 1: Calculate total man-hours for the original scenario

  • 200 men 8 hours/day 6 days = 9600 man-hours

Step 2: Calculate the number of days for the new scenario

  • Let the number of days be 'x'

  • 300 men 6 hours/day x days = 9600 man-hours

  • 1800x = 9600

  • x = 9600 / 1800

  • x = $5 \frac13$ days

Therefore, it will take approximately $5 \frac13$ days for 300 men working 6 hours per day to dig the


Related Questions:

If Anil takes 5 days to complete a task when he works for 8 hours a day, how many days will he take to complete the task if he works 6 hours a day?
After 63 litres of petrol was poured into an empty storage tank, it was still 10% empty. How much petrol (in litres)must be poured into the storage tank in order to fill it?
A യും B യും ചേർന്ന് ഒരു ജോലി ഏഴു ദിവസം കൊണ്ട് ചെയ്തു തീർക്കും . A യ്ക്ക് B യുടെ 1 3/4 മടങ്ങ് കാര്യക്ഷമതയുണ്ട് അതേ ജോലി A യ്ക്ക് മാത്രം എത്ര ദിവസം കൊണ്ട് ചെയ്യാൻ കഴിയും ?
image.png
'A' can do a piece of work in 10 days. He works at it for 8 days and then B finished the work in 16 days. How long will they take to complete the work if they do it together?