If 200 men can dig a canal working for 8 hours a day in 6 days, how long will it take to dig the canal, if 300 men work 6 hours per day?
A6 days
B$$5\frac13$ days$
C$$4\frac23$days$
D7days
A6 days
B$$5\frac13$ days$
C$$4\frac23$days$
D7days