A and B are jogging around a park's circular track which has a perimeter of 1.2 km. They start from the same point at 6:00 a.m. and run in opposite directions. A's speed is 5 km/h, and B's speed is 7 km/h. At what time will they meet for the fifth time?

A6:25 AM

B6:30 AM

C6:45 AM

D7:00 AM

Answer:

B. 6:30 AM

Read Explanation:

Track perimeter (= 1.2) km

Since they run in opposite directions, relative speed:

5+7=12 km/h5 + 7 = 12 \text{ km/h}

Time for one meeting:

1.212=0.1 hour\frac{1.2}{12} = 0.1 \text{ hour}

0.1 hour=6 minutes0.1 \text{ hour} = 6 \text{ minutes}

So they meet every 6 minutes.

For the 5th meeting:

5×6=30 minutes5 \times 6 = 30 \text{ minutes}

Starting time = 6:00 a.m.

6:00+30 minutes=6:30 a.m.6:00 + 30 \text{ minutes} = 6:30 \text{ a.m.}

So, they will meet for the fifth time at:

6:30 a.m.\boxed{6:30\ \text{a.m.}}


Related Questions:

A pipe can fill a tank in 9 hours. Another pipe can empty the filled tank in 63 hours. If both the pipes are opened simultaneously, then the time (in hours) in which the tank will be two-third filled, is:
A യും B യും C യും കൂടി ഒരു ജോലി 4 ദിവസം കൊണ്ടു ചെയ്തുതീർക്കുന്നു. A തനിയെ 12 ദിവസം കൊണ്ടും B തനിയെ 18 ദിവസം കൊണ്ടും ചെയ്തുതീർത്താൽ C യ്ക്ക് തനിയെ ആ ജോലി ചെയ്യാൻ വേണ്ടി വരുന്ന ദിവസമെത്ര?
നാല് പേർ ചേർന്ന് ഒമ്പത് ദിവസം കൊണ്ട് തീർക്കുന്ന ഒരു ജോലി ആറ് ദിവസം കൊണ്ട്തീർക്കണമെങ്കിൽ എത്ര ജോലിക്കാരെ കൂടി കൂടുതലായി വേണ്ടിവരും ?
ഒരു പ്രത്യേക ജോലി ചെയ്തു തീർക്കാൻ അജയന് 6 ദിവസം വേണ്ടിവരും. അതേ ജോലി ചെയ്തു തീർക്കാൻ വിജയന് 3 ദിവസം മതിയാകും. രണ്ടുപേരും കൂടി ഒരേസമയം ഈ ജോലി ചെയ്തു തീർക്കാൻ എത്ര ദിവസം വേണം ?
If Anil takes 5 days to complete a task when he works for 8 hours a day, how many days will he take to complete the task if he works 6 hours a day?