If 25 persons can complete a work in 140 days, then how many persons will be required to complete the same work in 70 days?

A70

B50

C80

D40

Answer:

B. 50

Read Explanation:

M1D1 = M2D2 25 × 140 = 70 × M2 M2 = (25×140)/70 M2 = 25 × 2 = 50


Related Questions:

Isha can do a certain piece of work in 20 days. Isha and Smriti can together do the same work in 16 days, and Isha, Smriti and Ashlesha can do the same work together in 8 days. In how many days can Isha and Ashlesha do the same work?
A and B can do a piece of work in 12 days and 15 days respectively. They began to work together but A left after 4 days. In how many more days would B alone complete the remaining work?
Two pipes are connected to a water tank. The first pipe can fill the tank in 10 minutes and the second pipe can empty it in 15 minutes. If both pipes opened simultaneously, then find the time in which the tank will be completely filled with water.
Madhu and Shiney together can complete a piece of work in 20 days, Shiney and Rosy together can complete the same work in 12 days, and Rosy and Madhu together can complete the work in 15 days. In how many days will three of them complete it together?
A and B together can do a certain work in 20 days, B and C together can do it in 30 days, and C and A together can do it in 24 days, B alone will complete 2/3 part of the same work is∶