A & B together do a work in 40 days. B & C together do in 25 days. A and B started working together, and A left work after 6 days & B left work after 8 days. After A left, C join the work & C completed the work in 40.5 days, C alone can complete the work in how many days?

A80 days

B120 days

C70 days

D50 days

Answer:

D. 50 days

Read Explanation:

image.png

Let the efficiency of C be x

Now,

6 × 5 + 2 × 8 + 38.5 × x = 200

⇒ 30 + 16 + 38.5x = 200

⇒ 38.5x = 200 - 46

⇒ 38.5x = 154

⇒ x = 4

So, the efficiency of C = 4

So, time taken by C = 200/4 = 50 days



Related Questions:

A can do a piece of work in 12 days. B can do it in 18 days. With the assistance of C, they completed the work in 4 days. C alone can do it in ______________days.
A tap can fill a tank in 48 minutes, where as another tap can empty it in 2 hours. If both the taps are opened at 11:40 am then the tank will be filled at
15 ആളുകൾ ചേർന്ന് ഒരു ജോലി 18 ദിവസം കൊണ്ട് തീർക്കും. എന്നാൽ അതേ ജോലി 10 ആളുകൾ എത്ര ദിവസം കൊണ്ട് തീർക്കും ?
The efficiency of A and B to do a work is in the ratio 3 ∶ 5. Working together they can complete a work in 30 days. In how many days A alone will complete that work?
Two pipes A and B can fill a tank in 15 hours and 20 hours, respectively, while a third pipe C can empty the full tank in 30 hours. If all the three pipes operate simultaneously, in how much time will the tank, initially empty, be filled?