Let the amount of work done by A, B, and C in one day be a, b, and c respectively.
Given Information:
A and B together can complete the work in 12 days. This means their combined work rate is 1/12 per day. So, a + b = 1/12.
B and C together can complete the work in 15 days. Their combined work rate is 1/15 per day. So, b + c = 1/15.
C and A together can complete the work in 20 days. Their combined work rate is 1/20 per day. So, c + a = 1/20.
Finding the Combined Work Rate of A, B, and C:
Add the three equations: (a + b) + (b + c) + (c + a) = 1/12 + 1/15 + 1/20
This simplifies to 2(a + b + c) = (5 + 4 + 3) / 60 = 12/60 = 1/5.
Therefore, the combined work rate of A, B, and C is (1/5) / 2 = 1/10 per day.
Calculating the Time Taken Together:
If their combined work rate is 1/10 of the work per day, they will complete the entire work in the reciprocal of this rate.
Time taken = 1 / (1/10) = 10 days.