Challenger App

No.1 PSC Learning App

1M+ Downloads
A and B can do a work in 12 days, B and C can do the same work in 15 days, and C and A can do the same work in 20 days. A, B and C will complete the work together in:

A8 days

B15 days

C20 days

D10

Answer:

D. 10

Read Explanation:

Let the amount of work done by A, B, and C in one day be a, b, and c respectively.

  1. Given Information:

    • A and B together can complete the work in 12 days. This means their combined work rate is 1/12 per day. So, a + b = 1/12.

    • B and C together can complete the work in 15 days. Their combined work rate is 1/15 per day. So, b + c = 1/15.

    • C and A together can complete the work in 20 days. Their combined work rate is 1/20 per day. So, c + a = 1/20.

  2. Finding the Combined Work Rate of A, B, and C:

    • Add the three equations: (a + b) + (b + c) + (c + a) = 1/12 + 1/15 + 1/20

    • This simplifies to 2(a + b + c) = (5 + 4 + 3) / 60 = 12/60 = 1/5.

    • Therefore, the combined work rate of A, B, and C is (1/5) / 2 = 1/10 per day.

  3. Calculating the Time Taken Together:

    • If their combined work rate is 1/10 of the work per day, they will complete the entire work in the reciprocal of this rate.

    • Time taken = 1 / (1/10) = 10 days.


Related Questions:

Isha can do a certain piece of work in 15 days. Isha and Smriti can together do the same work in 11 days, and Isha, Smriti and Ashlesha can do the same work together in 10days. In how many days can Isha and Ashlesha do the same work?
മനുവിന് ഒരു ജോലി ചെയ്യാൻ 10 ദിവസം വേണം അനുവിന് അത് ചെയ്ത് തീർക്കാൻ 15 ദിവസം വേണം. എങ്കിൽ രണ്ടു പേരും ചേർന്ന് ഈ ജോലി എത്ര ദിവസം കൊണ്ട് ചെയ്തു തീർക്കും?
A can do a piece of work in 12 days and B can do it in 18 days. They work together for 2 days and then A leaves. How long will B take to finish the remaining work ?
A pipe can fill a tank with water in 3 hours. Due to leakage in bottom, it takes 3 ½ hours to fill it. In what time the leak will empty the fully filled tank ?
40 പേർ ഒരു ദിവസം 10 മണിക്കൂർ ജോലി ചെയ്‌താൽ ഒരു ജോലി 12 ദിവസം കൊണ്ട് തീർക്കാൻ ആകും. ഇതേ ജോലി ഒരാൾ ഒരു ദിവസം 11 മണിക്കൂർ ചെയ്‌ത 16 ദിവസം കൊണ്ട് തീർക്കണമെങ്കിൽ എത്ര പേരെ ഒഴിവാക്കണം?