A and B can do a work together in 18 days. A is three times as efficient as B. In how many days can B alone complete the work?

A54 days

B64 days

C72 days

D60 days

Answer:

C. 72 days

Read Explanation:

Solution:

Given:

A and B can do the work together in 18 days. A is three times as efficient as B.

Concept Used:

Time ∝ 1/efficiency

If a person can complete a work in x days then in 1 day he will do 1/x part of the work

Calculation:

A is three times as efficient as B which imply the rate of efficiency of A and B is 3 : 1

Required time ratio of A and B to complete the work alone is 1/3 : 1

⇒ 1 : 3

Let, A can do the work in x day and B can do the same in 3x day

In 1 day A can do 1/x part of the work

In 1 day B can do 1/3x part of the work

Together in 1 day they can do (1/x + 1/3x) part of the work

⇒ 4/3x part of the work

A and B can do the work together in 18 days.

In 1 day they can do 1/18 part of the work together

4/3x = 1/18

⇒ x = 24

B alone take time to complete the work (3 × 24)

⇒ 72 days

∴ In 72 days B can complete the work alone.

Alternate Method:

image.png

Related Questions:

In what ratio must oil worth Rs. 80/kg is mixed with oil worth Rs. 85/kg and selling the mixture at Rs. 98.25/kg, there can be a profit of 20% ?
Suresh can complete a job in 15 hours. Ashutosh alone can complete the same job in 10 hours. If Suresh works alone for 9 hours and then stops, how many hours will it take Ashutosh to complete the job alone?
A can make a divider in 20 days, while B can make it in 50 days. If they work together and get Rs.3500, then find the share of B in the amount.
Vikram and Vivek can finish a work in 50 days. They worked together for 20 days and then left. How much work has been done by them?
5 മുതിർന്നവർ ഒരു ജോലി 3 ദിവസം കൊണ്ട് ചെയ്തു തീർക്കും 3 കുട്ടികൾ ഇതേ ജോലി 5 ദിവസം കൊണ്ട് ചെയ്തു തീർക്കും 4 മുതിർന്നവരും 2 കുട്ടികളും ഈ ജോലി ചെയ്തു തീർക്കാൻ എടുക്കുന്ന സമയം എത്ര?