A and B can together finish a work 30 days. They worked together for 20 days and then B left. After another 20 days, A finished the remaining work. In how many days A alone can finish the work?
A45
B75
C60
D90
Answer:
C. 60
Read Explanation:
Concepts in Time and Work
Understanding Work Rate
If a person can complete a work in 'x' days, their work rate is 1/x of the work per day.
The total work is considered as 1 unit.
Applying the Concepts to the Problem
Let the number of days A takes to finish the work alone be 'a' days.
Let the number of days B takes to finish the work alone be 'b' days.
Work done by A in 1 day = 1/a
Work done by B in 1 day = 1/b
Together, their work rate is (1/a + 1/b) per day.
Problem Breakdown and Calculation
A and B together finish the work in 30 days.
So, their combined work rate is 1/30 work per day.
They worked together for 20 days. Work done in these 20 days = 20 × (1/30) = 2/3 of the work.
Remaining work = 1 - 2/3 = 1/3 of the work.
After B left, A worked alone for another 20 days to finish the remaining 1/3 work.
This implies that A alone can do 1/3 of the work in 20 days.
Therefore, A alone can finish the entire work (3/3) in 20 days × 3 = 60 days.