App Logo

No.1 PSC Learning App

1M+ Downloads
A and B can together finish a work 30 days. They worked together for 20 days and then B left. After another 20 days, A finished the remaining work. In how many days A alone can finish the work?

A45

B75

C60

D90

Answer:

C. 60

Read Explanation:

Concepts in Time and Work

Understanding Work Rate

  • If a person can complete a work in 'x' days, their work rate is 1/x of the work per day.

  • The total work is considered as 1 unit.

Applying the Concepts to the Problem

  • Let the number of days A takes to finish the work alone be 'a' days.

  • Let the number of days B takes to finish the work alone be 'b' days.

  • Work done by A in 1 day = 1/a

  • Work done by B in 1 day = 1/b

  • Together, their work rate is (1/a + 1/b) per day.

Problem Breakdown and Calculation

  1. A and B together finish the work in 30 days.

  2. So, their combined work rate is 1/30 work per day.

  3. They worked together for 20 days. Work done in these 20 days = 20 × (1/30) = 2/3 of the work.

  4. Remaining work = 1 - 2/3 = 1/3 of the work.

  5. After B left, A worked alone for another 20 days to finish the remaining 1/3 work.

  6. This implies that A alone can do 1/3 of the work in 20 days.

  7. Therefore, A alone can finish the entire work (3/3) in 20 days × 3 = 60 days.


Related Questions:

A can do a piece of work in 12 days and B can do it in 18 days. They work together for 2 days and then A leaves. How long will B take to finish the remaining work ?
രേഖയ്ക്കും സൊണാലിക്കും 20 ദിവസത്തെ കൂലിയായി ലഭിച്ചത് 2800 രൂപയാണ്. സൊണാലിയുടെ മൂന്നിരട്ടിയായിരുന്നു രേഖയുടെ ജോലിയിലെ കാര്യക്ഷമത. സൊണാലിയുടെ ദിവസ വേതനം എത്രയാണ്?
20 ആളുകൾ 20 ദിവസം കൊണ്ട് ചെയ്തു തീർക്കുന്ന ജോലി ചെയ്യാൻ 5 പേർക്ക് എത്ര ദിവസം വേണം ?
Jitesh and Kamal can complete a certain piece of work in 7 and 11 days, respectively, They started to work together, and after 3 days, Kamal left. In how many days will Jitesh complete the remaining work?
Madhu and Shiney together can complete a piece of work in 20 days, Shiney and Rosy together can complete the same work in 12 days, and Rosy and Madhu together can complete the work in 15 days. In how many days will three of them complete it together?