Challenger App

No.1 PSC Learning App

1M+ Downloads
There are 3 taps, A, B and C, in a tank. These can fill the tank in 10 h, 20 h and 25 h, respectively. At first, all three taps are opened simultaneously. After 2 h, tap C is closed and tap A and B keep running. After 4 h, tap B is also closed. The remaining tank is filled by tap A alone. Find the percentage of work done by tap A itself.

A75%

B52%

C72%

D32%

Answer:

C. 72%

Read Explanation:

Total volume of tank filled by taps = LCM(10, 20 and 25) = 100 tap A in 1 hr = 100/10 = 10 tap B in 1 hr = 100/20 = 5 tap C in 1 hr = 100/25 = 4 Tap A, B and C can fill together = 10 + 5 + 4 = 19 units After 2 hrs, tap C is closed, Amount of tank filled = 2 × 19 = 38 After 4 hrs, tap B is also closed, For 2 hours, tap A and B was open. Units of water filled = (10 + 5) × 2 = 30 Amount of water filled by A alone = 100 – (30 + 38) = 32 Total units of water filled by tap A = 20 + 20 + 32= 72


Related Questions:

A യും B യും ചേർന്ന് 30 ദിവസം കൊണ്ട് ഒരു ജോലി പൂർത്തിയാക്കാൻ കഴിയും. അവർ ഒരുമിച്ച് ആരംഭിച്ചെങ്കിലും 6 ദിവസത്തിന് ശേഷം A ജോലി ഉപേക്ഷിച്ചു, 36 ദിവസങ്ങൾ കൂടി കഴിഞ്ഞ് B ജോലി പൂർത്തിയാക്കുന്നുവെങ്കിൽ, A എത്ര ദിവസം കൊണ്ട് അതേ ജോലി പൂർത്തിയാക്കാൻ കഴിയും?
There are three pipes A, B, C in a tank. If all the three pipes are open together the tank will be filled in 9 minutes. A and C are open together the tank will be fill in 12 minutes if B alone is open the tank will be filled in how many minutes ?
54kg ധാന്യം 35 കുതിരകൾക്ക് 21 ദിവസത്തേക്ക് തികയുമെങ്കിൽ 72kg ധാന്യം 28 കുതിരകൾക്ക് എത്ര ദിവസത്തേക്ക് തികയും?
Jitesh and Kamal can complete a certain piece of work in 7 and 11 days, respectively, They started to work together, and after 3 days, Kamal left. In how many days will Jitesh complete the remaining work?
If C alone can complete two-third part of a work in 12 days, then in how many days C can complete the whole work?