Challenger App

No.1 PSC Learning App

1M+ Downloads
A and B together can complete a work in 12 days. A alone can complete it in 20 days. If B does the work only for the first half of the day daily, then in how many days will A and B together complete the work?

A15 days

B22/3 days

C43/2 days

D40/3 days

Answer:

A. 15 days

Read Explanation:

A and B can complete a work in = 12 days A alone can complete = 20 LCM of these two are the total work = 60 efficiency of A and B = 60/12=5 efficiency of A =60/20=3 efficiency of B = 5-3 =2 half day efficiency =2/2=1 half day of B and full day of A = 3+1=4 so the total number of days = 60/4=15 days


Related Questions:

മൂന്നു സംഖ്യകളുടെ അനുപാതം 3:5 :7 ആണ്.ആദ്യത്തെ സംഖ്യയും മൂന്നാമത്തെ സംഖ്യയും കൂട്ടിയാൽ രണ്ടാമത്തെ സംഖ്യയേക്കാൾ 40 കൂടുതലാണെങ്കിൽ ,ഏറ്റവും വലിയ സംഖ്യ എത്ര ?
Abhishek and Deepanshi undertake to do a piece of work for ₹1,000. Abhishek alone can do it in 5 days and Deepanshi alone can do it in 10 days. With the help of Chitransh, they finish it in 2 days. How much should Chitransh be paid for his contribution?
20 ആളുകൾ 6 ദിവസം കൊണ്ട് ചെയ്തു തീർക്കുന്ന ഒരു ജോലി 8 ആളുകൾ എത്ര ദിവസം കൊണ്ട് ചെയ്തു തീർക്കും
7 ആളുകൾക്ക് ഒരു ജോലി പൂർത്തിയാക്കാൻ '6' ദിവസം വേണം. അതേ ജോലി ഒരു ദിവസം കൊണ്ട്പൂർത്തിയാക്കാൻ എത്ര ആൾക്കാർ വേണം?-
4 ടാപ്പുകൾക്ക് 10 മണിക്കൂർ കൊണ്ട് ഒരു ടാങ്ക് നിറക്കാൻ കഴിയും. അപ്പോൾ 6 ടാപ്പുകൾക്ക് ഇതേ ടാങ്കിൽ എത്ര മണിക്കൂർ കൊണ്ട് നിറയ്ക്കാനാകും?