Challenger App

No.1 PSC Learning App

★
★
★
★
★
1M+ Downloads
A and B together can complete a work in 12 days. A alone can complete it in 20 days. If B does the work only for the first half of the day daily, then in how many days will A and B together complete the work?

A15 days

B22/3 days

C43/2 days

D40/3 days

Answer:

A. 15 days

Read Explanation:

A and B can complete a work in = 12 days A alone can complete = 20 LCM of these two are the total work = 60 efficiency of A and B = 60/12=5 efficiency of A =60/20=3 efficiency of B = 5-3 =2 half day efficiency =2/2=1 half day of B and full day of A = 3+1=4 so the total number of days = 60/4=15 days


Related Questions:

സന്ധ്യ ഒരു ജോലി 20 ദിവസം കൊണ്ട് ചെയ്തു തീർക്കും. ഗോപു അതു ചെയ്യാൻ 60 ദിവസം എടുക്കും. എങ്കിൽ രണ്ടു പേരും ചേർന്നാൽ ആ ജോലി എത്ര ദിവസം കൊണ്ട് പൂർത്തിയാക്കും ?
Rishi can do a piece of work in 8 hours. Shan can do it in 12 hours. With the assistance of Veer, they completed the work in 3 hours. In how many hours can Veer alone do it?
The number of days to finish a work by A is double the number of days to finish the work by B. The number of days to finish the work by C is half the number of days to finish the work by B. A can finish the work in 12 days. If B works on the 1st day, A works on the 2nd day and C works on the 3rd day, again B works on the 4th day and so on, then the work is finished in ______ days.
A ഒരു ദിവസം ചെയ്യുന്ന ജോലി, B ഒരു ദിവസം ചെയ്യുന്ന ജോലിയുടെ പകുതിയാണ്. A യും B യും ചേർന്ന് ഒരു ജോലി 22 ദിവത്തിൽ പൂർത്തിയാക്കാൻ കഴിയും. എന്നാൽ A ഒറ്റയ്ക്ക് ആ ജോലി പൂർത്തിയാക്കാൻ എത്ര ദിവസം എടുക്കും ?
R ഒരു ജോലി പൂർത്തിയാക്കാൻ എടുക്കുന്ന സമയം, M-ന്റെ സമയത്തിന്റെ 2 മടങ്ങും S-ന്റെ സമയത്തിന്റെ 3 മടങ്ങുമാണ്. R, M, S എന്നിവർ ഒരുമിച്ച് പ്രവർത്തിച്ചാൽ ആ ജോലി 4 ദിവസത്തിൽ പൂർത്തിയാക്കും. ഓരോരുത്തരും ഒറ്റയ്ക്ക് ജോലി പൂർത്തിയാക്കാൻ എടുക്കുന്ന സമയം?