App Logo

No.1 PSC Learning App

1M+ Downloads
A and B together can complete a work in 12 days. A alone can complete it in 20 days. If B does the work only for the first half of the day daily, then in how many days will A and B together complete the work?

A15 days

B22/3 days

C43/2 days

D40/3 days

Answer:

A. 15 days

Read Explanation:

A and B can complete a work in = 12 days A alone can complete = 20 LCM of these two are the total work = 60 efficiency of A and B = 60/12=5 efficiency of A =60/20=3 efficiency of B = 5-3 =2 half day efficiency =2/2=1 half day of B and full day of A = 3+1=4 so the total number of days = 60/4=15 days


Related Questions:

Three taps A, B and C can fill a tank in 10, 18 and 6 hours, respectively. If A is open all the time and B and C are open for one hour each alternatively, starting with B, the tank will be full in:
12 ആളുകൾ 25 ദിവസംകൊണ്ട് ചെയ്തുതീർക്കുന്ന ജോലി 15 ദിവസംകൊണ്ട് തീർക്കാൻ ഇനി എത ആളുകൾ കൂടി വേണം?
A and B undertake to complete a piece of work for ₹600. A alone can complete it in 4 days while B alone can complete it in 6 days. With the help of C, they finish the work in 2 days. Find the share of C in the payment received.
A and B can do a work in 15 days and 10 days respectively. They begin the work together but B leaves after two days. Now A completes the remaining work. The total number of days needed for the completion of the work is:
A ഒരു ജോലി 25 ദിവസംകൊണ്ടും B അതേ ജോലി 30 ദിവസംകൊണ്ടും പൂർത്തിയാക്കും. അവർ ഒരുമിച്ച് 5 ദിവസം ജോലി ചെയ്തതിന് ശേഷം A വിട്ടുപോയി. ബാക്കി ജോലി Bക്ക് പൂർത്തിയാക്കാൻ എത്ര ദിവസം വേണം?