App Logo

No.1 PSC Learning App

1M+ Downloads
A and B together can complete a work in 12 days. A alone can complete it in 20 days. If B does the work only for the first half of the day daily, then in how many days will A and B together complete the work?

A15 days

B22/3 days

C43/2 days

D40/3 days

Answer:

A. 15 days

Read Explanation:

A and B can complete a work in = 12 days A alone can complete = 20 LCM of these two are the total work = 60 efficiency of A and B = 60/12=5 efficiency of A =60/20=3 efficiency of B = 5-3 =2 half day efficiency =2/2=1 half day of B and full day of A = 3+1=4 so the total number of days = 60/4=15 days


Related Questions:

A can complete a certain work in 35 days and B can complete the same work in 15 days. They worked together for 7 days, then B left the work. In how many days will A alone complete 60% of the remaining work?
The efficiency of A and B to do a work is in the ratio 3 ∶ 5. Working together they can complete a work in 30 days. In how many days A alone will complete that work?
A, 6 ദിവസം കൊണ്ടും B, 12 ദിവസം കൊണ്ടും ഒരു ജോലി ചെയ്യാൻ കഴിയും. ഒരുമിച്ചു പ്രവർത്തിച്ചാൽ എത്ര ദിവസം കൊണ്ട് ജോലി തീരും?
A ഒരു ജോലി 20 ദിവസം എടുത്തു പൂർത്തിയാക്കുന്നു A യും B യും കൂടി ഒരുമിച്ച് ജോലി പൂർത്തീകരിക്കാൻ 12 ദിവസം എടുക്കും എന്നാൽ B മാത്രമായി പ്രസ്തുത ജോലി പൂർത്തീകരിക്കാൻ എത്ര ദിവസം എടുക്കും ?
10 ദിവസം കൊണ്ടാണ് A ഒരു ജോലി പൂർത്തിയാക്കുന്നത്. A 6 ദിവസം ജോലി ചെയ്തു. ശേഷം വിട്ടുപോകുന്നു. ശേഷിക്കുന്ന ജോലി B 2 ദിവസം കൊണ്ട് തീർക്കുന്നു. B ഒറ്റയ്ക്ക് എത്ര ദിവസം കൊണ്ട് ജോലി പൂർത്തിയാക്കും?