Challenger App

No.1 PSC Learning App

1M+ Downloads
A and B together can complete a work in 12 days. A alone can complete it in 20 days. If B does the work only for the first half of the day daily, then in how many days will A and B together complete the work?

A15 days

B22/3 days

C43/2 days

D40/3 days

Answer:

A. 15 days

Read Explanation:

A and B can complete a work in = 12 days A alone can complete = 20 LCM of these two are the total work = 60 efficiency of A and B = 60/12=5 efficiency of A =60/20=3 efficiency of B = 5-3 =2 half day efficiency =2/2=1 half day of B and full day of A = 3+1=4 so the total number of days = 60/4=15 days


Related Questions:

Manoj can do a piece of work in 8 hours. Anand can do it in 8 hours. With the assistance of Anil, they completed the work in 2 hours. In how many hours can Anil alone do it?
നാല് പേർ ചേർന്ന് ഒമ്പത് ദിവസം കൊണ്ട് തീർക്കുന്ന ഒരു ജോലി ആറ് ദിവസം കൊണ്ട്തീർക്കണമെങ്കിൽ എത്ര ജോലിക്കാരെ കൂടി കൂടുതലായി വേണ്ടിവരും ?
A and B start a business. A invests 2 times more than B. After 8 months, A withdraws half of his capital, and B triples his capital. If the total profit after one year is ₹75,000, find the share of A.
P and Q can complete a piece of work in 28 days and 35 days, respectively. P begins to do the work and they work alternatively one at a time for one day each. In how many days will the whole work be completed?
Isha can do a certain piece of work in 15 days. Isha and Smriti can together do the same work in 11 days, and Isha, Smriti and Ashlesha can do the same work together in 10days. In how many days can Isha and Ashlesha do the same work?