A and B together can complete a work in 30 day. They started together but after 6 days A left the work and the work is completed by B after 36 more days. A alone can complete the entire work in how many days?

A45

B90

C120

D60

Answer:

B. 90

Read Explanation:

efficiency of A = x efficiency of B = y Work = efficiency ⨯ time 30 ⨯ (x + y) = 6(x + y) + 36 y 24(x + y) = 36y 24x = 12y 2x = y Let x = 1 and y = 2 Work = 30 ⨯ 3 = 90 units Time taken by A alone = 90/1 = 90 days


Related Questions:

A, B, and C can do a piece of work in 42, 56, and 63 days respectively. They started the work together but A left the work 10 days before the completion of the work while B left the work 12 days before the completion. Find the number of days (approximate) to complete the whole work.
6 പുരുഷന്മാരും 8 സ്ത്രീകളും ചേർന്ന് 10 ദിവസം കൊണ്ട് ഒരു ജോലി പൂർത്തിയാക്കാൻ കഴിയും. ഒരു സ്ത്രീ ഒരു ദിവസം ചെയ്യുന്ന ജോലി ഒരു പുരുഷൻ ഒരു ദിവസം ചെയ്യുന്നതിൻ്റെ പകുതി ജോലിക്ക് തുല്യമാണ്. 10 സ്ത്രീകൾ ഒറ്റയ്ക്ക് ജോലി ചെയ്യുന്നുണ്ടെങ്കിൽ എത്ര ദിവസം കൊണ്ട് പണി പൂർത്തിയാകും?
A can do a piece of work in 30 days, while B alone can do it in 40 days. In how many days can A and B working together do it?
ജോണും ദീപുവും ചേർന്ന് ഒരു ജോലി ചെയ്തു തീർക്കാൻ 45 ദിവസം എടുക്കുന്നു.എന്നാൽ ജോൺ ഒറ്റയ്ക്ക് ഈ ജോലി 70 ദിവസം കൊണ്ട് ചെയ്തു തീർക്കും. ദീപു ഒറ്റയ്ക്ക്ഇതേ ജോലി ചെയ്തു തീർക്കാൻ എത്ര ദിവസം എടുക്കും?
P is twice as efficient as Q. Q takes 12 days to complete a job. If both of them work together, how much time will they take to complete the job?