App Logo

No.1 PSC Learning App

1M+ Downloads
A and B together can do a certain work in 20 days, B and C together can do it in 30 days, and C and A together can do it in 24 days, B alone will complete 2/3 part of the same work is∶

A20

B16

C24

D32

Answer:

D. 32

Read Explanation:

Shortcut Trick LCM(20, 30, 24) = 120 Let work is 120u

Days

Work

Efficiency

(A+B) 20

 

6

(B+C) 30

120

4

(C+A) 24

 

5

Total efficiency 2(A + B + C) = 15u

A + B + C = 7.5u

A = A + B + C - (B+C) = 7.5 - 4 = 3.5u

By same process Efficiency of B = 2.5u, C = 1.5u

B alone can complete = (120 × 2/3)/2.5 = 32 days

Given:

⇒ 1/A + 1/B = 1/20

⇒ 1/B + 1/C = 1/30

⇒ 1/A + 1/C = 1/24

Calculation:

Solving,

⇒ 1/A - 1/C = 1/20 - 1/30 = 1/60

⇒ 1/A + 1/C = 1/24

Solving,

⇒ 2/A = 1/60 + 1/24 = 7/120

⇒ 1/A = 7/240

Then,

⇒ 1/B = 1/20 - 7/240 = 1/48

B's 1 days work = 1/48

B alone can complete the work in 48 days.

∴ Time taken by B to complete 2/3rd work = 2/3 × 48 = 32 days

Alternate Method

 Total work = LCM of 20, 30 and 24 = 120

In 1 day (A + B) can do 120/20 = 6 units work

In 1 day (B + C) can do 120/30 = 4 units work

In 1 day (A + C) can do 120/24 = 5 units work

In 1 day (A + C + B + C + C + A) = 2(A + B + C) can do 15 unit work

⇒ In 1 day (A + B + C) can do 15/2 = 7.5 units work

⇒ In 1 day B alone can do (A + B + C) - (A + C) = 7.5 - 5 = 2.5 units work

B alone can complete the work in 120/2.5 = 48 days

B alone can do 2/3rd part of the work in 48 × 2/3 = 32 days

∴ B alone will complete 2/3 part of the same work in 32 days.


Related Questions:

8 men and 12 women finish a job in 4 days. While 6 men and 14 women in 5 days. In how many days will 20 women finish the job?
A and B undertake to do a piece of work for Rs. 330. A can do it in 11 days and B can do it in 22 days. With the help of C, they finish it in 6 days. How much should C be paid for his work?
A ക്ക് ഒരു ജോലി 6 ദിവസം കൊണ്ടും B ക്ക് 4 ദിവസം കൊണ്ടും ചെയ്യാൻ കഴിയും. രണ്ടുപേരും ഒരുമിച്ച് പ്രവർത്തിച്ചാൽ എത്ര സമയമെടുക്കും?
Two pipes P and Q, together can fill a cistern in 20 minutes and P alone can in 30 miutes. Then Q alone can fill the cistern in?
Thers is an order of 19000 quantity of a particular product from a customer. The firm produces 1000 quantity of that product per day out of which 5% are unfit for sale. In how many days will the order be completed ?