App Logo

No.1 PSC Learning App

1M+ Downloads
A and B together can do a certain work in 20 days, B and C together can do it in 30 days, and C and A together can do it in 24 days, B alone will complete 2/3 part of the same work is∶

A20

B16

C24

D32

Answer:

D. 32

Read Explanation:

Shortcut Trick LCM(20, 30, 24) = 120 Let work is 120u

Days

Work

Efficiency

(A+B) 20

 

6

(B+C) 30

120

4

(C+A) 24

 

5

Total efficiency 2(A + B + C) = 15u

A + B + C = 7.5u

A = A + B + C - (B+C) = 7.5 - 4 = 3.5u

By same process Efficiency of B = 2.5u, C = 1.5u

B alone can complete = (120 × 2/3)/2.5 = 32 days

Given:

⇒ 1/A + 1/B = 1/20

⇒ 1/B + 1/C = 1/30

⇒ 1/A + 1/C = 1/24

Calculation:

Solving,

⇒ 1/A - 1/C = 1/20 - 1/30 = 1/60

⇒ 1/A + 1/C = 1/24

Solving,

⇒ 2/A = 1/60 + 1/24 = 7/120

⇒ 1/A = 7/240

Then,

⇒ 1/B = 1/20 - 7/240 = 1/48

B's 1 days work = 1/48

B alone can complete the work in 48 days.

∴ Time taken by B to complete 2/3rd work = 2/3 × 48 = 32 days

Alternate Method

 Total work = LCM of 20, 30 and 24 = 120

In 1 day (A + B) can do 120/20 = 6 units work

In 1 day (B + C) can do 120/30 = 4 units work

In 1 day (A + C) can do 120/24 = 5 units work

In 1 day (A + C + B + C + C + A) = 2(A + B + C) can do 15 unit work

⇒ In 1 day (A + B + C) can do 15/2 = 7.5 units work

⇒ In 1 day B alone can do (A + B + C) - (A + C) = 7.5 - 5 = 2.5 units work

B alone can complete the work in 120/2.5 = 48 days

B alone can do 2/3rd part of the work in 48 × 2/3 = 32 days

∴ B alone will complete 2/3 part of the same work in 32 days.


Related Questions:

Pravin can do a piece of work in 6 hours. Rishi can do it in 28 hours. With the assistance of Shan, they completed the work in 4 hours. In how many hours can Shan alone do it?
30 പേർ ചേർന്ന് 8 ദിവസം കൊണ്ട് ചെയ്തുതീർക്കുന്ന ഒരു ജോലി 40 പേർ ചേർന്ന് എത്ര ദിവസം കൊണ്ട് ചെയ്തു തീർക്കും ?
A can do 1/3 of a work in 30 days. B can do 2/5 of the same work in 24 days. They worked together for 20 days. C completed the remaining work in 8 days. Working together A, B and C will complete the same work in:
Vijay can do a piece of work in 4 hours. Ajay can do it in 28 hours. With the assistance of Amit, they completed the work in 3 hours. In how many hours can Amit alone do it?
40 പേർ ഒരു ദിവസം 10 മണിക്കൂർ ജോലി ചെയ്‌താൽ ഒരു ജോലി 12 ദിവസം കൊണ്ട് തീർക്കാൻ ആകും. ഇതേ ജോലി ഒരാൾ ഒരു ദിവസം 11 മണിക്കൂർ ചെയ്‌ത 16 ദിവസം കൊണ്ട് തീർക്കണമെങ്കിൽ എത്ര പേരെ ഒഴിവാക്കണം?