A and B together take 5 days to do work, B and C take 7 days to do the same, and A and C take 4 days to do it. Who among these will take the least time to do it alone?

AA

BB

CC

DThe data is not sufficient

Answer:

A. A

Read Explanation:

Solution:

Given:

A and B  take 5 days

B and C take 7 days

A and C take 4 days

Solution:

LCM(5, 7, 4) = 140 let total work be 140 unit

Time

Work

Efficiency

5

  140

28

7

20

4

35

The efficiency of A, B, C are

⇒ 2(A + B + C) = 28 + 20 + 35 = 83

⇒ A + B + C = 83/2 = 41.5

⇒ A = (A + B + C) - (B + C) = 41.5 - 20 = 21.5

By the same process

⇒ B = 41.5 - 35 = 6.5

⇒ C = 41.5 - 28 = 13.5

⇒ Time(A) = 140/21.5 = 6.51

⇒ Time(B) = 140/6.5 = 21.54

⇒ Time(C) = 140/13.5 = 10.37

A took the least time to complete the work. So, A is the fastest.

∴ A finishes fastest in 6.51 days.


Related Questions:

അരുണിന് 80 ദിവസം കൊണ്ട് ഒരു ജോലി ചെയ്യാൻ കഴിയും . അവൻ 10 ദിവസം അതിൽ ജോലി ചെയ്യുന്നു തുടർന്ന് ബാക്കിയുള്ള ജോലി അനിൽ മാത്രം 42 ദിവസം കൊണ്ട് പൂർത്തിയാക്കുന്നു . അരുണും അനിലും ചേർന്ന് ജോലി ചെയ്താൽ എത്ര സമയത്തിനുള്ളിൽ ജോലി പൂർത്തിയാക്കും ?
A can complete a certain work in 35 days and B can complete the same work in 15 days. They worked together for 7 days, then B left the work. In how many days will A alone complete 60% of the remaining work?
P and Q can do a work individually in 15 days and 20 days respectively. Find the respective ratio of their efficiencies.
A cistern is normally filled in 8 hours but takes another 2 hours longer to fill because of a leak in its bottom. If the cistern is full, the leak will empty it in :
30 പേർ ചേർന്ന് 8 ദിവസം കൊണ്ട് ചെയ്തു തീർക്കുന്ന ഒരു ജോലി 40 പേർ ചേർന്ന് എത്ര ദിവസം കൊണ്ട് ചെയ്തു തീർക്കും ?