Given:

A and B  take 5 days

B and C take 7 days

A and C take 4 days

Solution:

LCM(5, 7, 4) = 140 let total work be 140 unit

Time

Work

Efficiency

5

  140

28

7

20

4

35

The efficiency of A, B, C are

⇒ 2(A + B + C) = 28 + 20 + 35 = 83

⇒ A + B + C = 83/2 = 41.5

⇒ A = (A + B + C) - (B + C) = 41.5 - 20 = 21.5

By the same process

⇒ B = 41.5 - 35 = 6.5

⇒ C = 41.5 - 28 = 13.5

⇒ Time(A) = 140/21.5 = 6.51

⇒ Time(B) = 140/6.5 = 21.54

⇒ Time(C) = 140/13.5 = 10.37

A took the least time to complete the work. So, A is the fastest.

∴ A finishes fastest in 6.51 days.


Related Questions:

Two pipes X and Y can fill a cistern in 24 minutes and 32 minutes respectively. If both the pipes are opened together, then after how much time (in minutes) should Y be closed so that the tank is full in 18 minutes ?
Pipe A can fill a cistern in 6 hours and pipe B can fill it in 8 hours. Both the pipes are opened simultaneously, but after two hours, pipe A is closed. How many hours will B take to fill the remaining part of the cistern ?
A and B working separately can do a piece of work in 10 days and 15 days respectively. If they work on alternate days beginning with A, in how many days will the work be completed ?
ഒരു ടാങ്ക് അതിന്റെ 3/4 ഭാഗം വെള്ളം നിറച്ചിരിയ്ക്കുന്നു. 5 ലിറ്റർ വെള്ളം കൂടി ഒഴിച്ചാൽ അതിന്റെ 4/5 ഭാഗം നിറയുമെങ്കിൽ ടാങ്കിന്റെ യഥാർത്ഥ ശേഷി എത്ര ?

A can complete 331333\frac{1}{3} % of a work in 5 days and B can complete 40% of the same work in 10 days. They work together for 5 days and then B left the work. A alone will complete the remaining work in: