App Logo

No.1 PSC Learning App

1M+ Downloads
A and B working together can complete a job in 30 days. The ratio of their efficiencies is 3 : 2. In how many days can the faster person complete the job?

A50

B30

C40

D60

Answer:

A. 50

Read Explanation:

Solution:

Given:

A and B working together can complete a job in 30 days. The ratio of their efficiencies is 3 : 2.

Calculation

Let total work to be done = 150 units

Let efficiency of A and B respectively be 3x and 2x units/day

⇒ (3x + 2x) × 30 = 150

⇒ x = 1

Time taken by faster person, i.e A =1503×1=50days=\frac{150}{3\times{1}}=50days

The time taken by faster person is 50 days.

Alternate Method:

image.png

Fastest person is A Efficiency of A is 3

1503=50days\frac{150}{3}=50 days


Related Questions:

Kiran can do a certain piece of work in 15 days. Kiran and Garima can together do the same work in 10 days, and Kiran, Garima and Mehak can do the same work together in 9 days. In how many days can Kiran and Mehak do the same work?
ഒരു ക്ളോക്കിൽ 12 അടിക്കാൻ 22 സെക്കന്റ് സമയമെടുക്കും.6 അടിക്കാൻ എത്ര സെക്കന്റ് സമയം വേണം ?
നാല് പേർ ചേർന്ന് ഒമ്പത് ദിവസം കൊണ്ട് തീർക്കുന്ന ഒരു ജോലി ആറ് ദിവസം കൊണ്ട്തീർക്കണമെങ്കിൽ എത്ര ജോലിക്കാരെ കൂടി കൂടുതലായി വേണ്ടിവരും ?
A and B can do a work in 15 days and 10 days respectively. They begin the work together but B leaves after two days. Now A completes the remaining work. The total number of days needed for the completion of the work is:
A and B can do a piece of work in 8 days and A alone can do it in 12 days. In how many days can B alone do it?