A, B and C can do a piece of work in 12 days, 14 days and 16 days respectively. All three of them started the work together and after working for four days C leaves the job, B left the job 4 days before completion of the work. Find the approximate time required to complete the work. (in days)

A9 days

B11 days

C8 days

D7 days

Answer:

D. 7 days

Read Explanation:

The time is taken by A to complete the work = 12 days The time is taken by B to complete the work = 14 days The time is taken by C to complete the work = 16 days The total amount of work = L.C.M of (12, 14 and 16) = 336 units Efficiency of A =336/12 = 28 Efficiency of B = 336/14 = 24 Efficiency of C = 336/16 = 21 28x + 21(4) + 24(x - 4) = 336 28x + 84 + 24x - 96 = 336 52x - 12 = 336 52x = 336 + 12 = 348 52x = 348 x ≈ 7 days


Related Questions:

തോമസ് കമ്പിവേലി കെട്ടാൻ വേണ്ടി ഒരാളെ ഏർപ്പെടുത്തി. ഉച്ചയായപ്പോൾ 1/3 ഭാഗം പണി കഴിഞ്ഞു. വൈകുന്നേരമായപ്പോൾ ബാക്കിയുള്ളതിൻറെ പകുതി ഭാഗവും തീർത്തു. ഇനി എത്ര ഭാഗം ബാക്കിയുണ്ട്?
Robert takes twice as much time as Tom and thrice as much time as George to complete a work. If working together, they can complete it in 23 hours, then find the time that Tom will take to complete the work.
If 3 men or 4 women can plough a field in 43 days, how long will 7 men and 5 women take to plough it ?
A, 6 ദിവസം കൊണ്ടും B, 12 ദിവസം കൊണ്ടും ഒരു ജോലി ചെയ്യാൻ കഴിയും. ഒരുമിച്ചു പ്രവർത്തിച്ചാൽ എത്ര ദിവസം കൊണ്ട് ജോലി തീരും?
A can finish 3/5th of a task in 6 days and B can finish 2/3th of the same task in 12 days. A and B worked together for 5 days. C alone completed the remaining task in 8 days. B and C, working together, will complete the same task in: