A, B and C can do a piece of work in 12 days, 14 days and 16 days respectively. All three of them started the work together and after working for four days C leaves the job, B left the job 4 days before completion of the work. Find the approximate time required to complete the work. (in days)

A9 days

B11 days

C8 days

D7 days

Answer:

D. 7 days

Read Explanation:

The time is taken by A to complete the work = 12 days The time is taken by B to complete the work = 14 days The time is taken by C to complete the work = 16 days The total amount of work = L.C.M of (12, 14 and 16) = 336 units Efficiency of A =336/12 = 28 Efficiency of B = 336/14 = 24 Efficiency of C = 336/16 = 21 28x + 21(4) + 24(x - 4) = 336 28x + 84 + 24x - 96 = 336 52x - 12 = 336 52x = 336 + 12 = 348 52x = 348 x ≈ 7 days


Related Questions:

A pipe can fill a tank in 9 hours. Another pipe can empty the filled tank in 27 hours. If both the pipes are opened simultaneously, then the time (in hours) in which the tank will be two-third filled, is:
60 ആളുകൾ 15 ദിവസം കൊണ്ട് തീർക്കുന്ന ജോലി 12 ദിവസം കൊണ്ട് തീർക്കണമെങ്കിൽ എത്ര പേരെ കൂടുതൽ നിയമിക്കണം ?
സുരേഷ് ഒരു ജാലി 9 ദിവസം കൊണ്ടും സതീഷ് 15 ദിവസംകൊണ്ടും ഗിരീഷ് 10 ദിവസംകൊണ്ടും പൂർത്തിയാക്കുന്നു. മൂന്നുപേരും കൂടി എത്ര ദിവസംകൊണ്ട് ആ ജോലി ചെയ്തുതീർക്കും
A can do a certain job in 12 days. B is 60% more efficient than A. To do the same job B alone would take?
12 പുരുഷന്മാരോ,18 സ്ത്രീകളോ ഒരു ജോലി 14 ദിവസം കൊണ്ട് ചെയ്തു തീർക്കുന്നു. എന്നാൽ 8 പുരുഷന്മാരും 16 സ്ത്രീകളും ചേർന്ന് അതേ ജോലി എത്ര സമയത്തിനുള്ളിൽ ചെയ്തു തീർക്കും ?