App Logo

No.1 PSC Learning App

1M+ Downloads
A, B, and C can do a piece of work in 42, 56, and 63 days respectively. They started the work together but A left the work 10 days before the completion of the work while B left the work 12 days before the completion. Find the number of days (approximate) to complete the whole work.

A29 days

B25 days

C15 days

D24 days

Answer:

B. 25 days

Read Explanation:

Solution: Given data: Time taken by A to complete the work = 42 days Time taken by B to complete the work = 56 days Time taken by C to complete the work = 63 days A left the work 10 days before completion B left the work 12 days before completion The concept: LCM (Least Common Multiple) and work done concept Find LCM of 42, 56, and 63 to find the total units of work. Use work = efficiency × time to find the work done by each individual. Calculation: LCM of 42, 56, 63 = 504 units ⇒ Daily work done by A = 504 / 42 = 12 units/day ⇒ Daily work done by B = 504 / 56 = 9 units/day ⇒ Daily work done by C = 504 / 63 = 8 units/day Let's assume the work is completed in D days. ⇒ Total work done by A = 12 × (D - 10) (as A left 10 days before completion) ⇒ Total work done by B = 9 × (D - 12) (as B left 12 days before completion) ⇒ Total work done by C = 8 × D Summing up work done by A, B, and C should be equal to total units of work (504). ⇒ 12(D - 10) + 9(D - 12) + 8D = 504 ⇒ 12D - 120 + 9D - 108 + 8D = 504 ⇒ (12 + 9 + 8)D = 504 + 120 + 108 ⇒ 29D = 732 ⇒ D = 732 / 29 ⇒ D ≈ 25 days Therefore, the work will be completed in approximately 25 days.


Related Questions:

A can do a piece of work in 12 days. B can do it in 18 days. With the assistance of C, they completed the work in 4 days. C alone can do it in ______________days.
ശശിയും സോമനും കൂടി ഒരു ജോലി 12 ദിവസം കൊണ്ട് തീർക്കും. ശശിക്ക് ഒറ്റയ്ക്ക് ആ ജോലി തീർക്കാൻ 20 ദിവസം വേണമെങ്കിൽ സോമന് ആ ജോലി തീർക്കാൻ എത്ര ദിവസം വേണം?
Five men working together can complete a work in 8 days. Om Prakash who can complete the same work independently in 24 days joined them after 4 days. Under the circumstances in how many days the work will be completed?
20 ആളുകൾ 20 ദിവസം കൊണ്ട് ചെയ്തു തീർക്കുന്ന ജോലി ചെയ്യാൻ 5 പേർക്ക് എത്ര ദിവസം വേണം ?
A can do a piece of work in 16 days and the same work can be done by B in 24 days, If they work individually on alternate days (i.e., on the first day A does the work and on the second day A was on leave and B done the second-day work and so on.) and A starts the work, then find the total days required to complete the work.