Challenger App

No.1 PSC Learning App

1M+ Downloads
A, B, and C can do a piece of work in 42, 56, and 63 days respectively. They started the work together but A left the work 10 days before the completion of the work while B left the work 12 days before the completion. Find the number of days (approximate) to complete the whole work.

A29 days

B25 days

C15 days

D24 days

Answer:

B. 25 days

Read Explanation:

Solution: Given data: Time taken by A to complete the work = 42 days Time taken by B to complete the work = 56 days Time taken by C to complete the work = 63 days A left the work 10 days before completion B left the work 12 days before completion The concept: LCM (Least Common Multiple) and work done concept Find LCM of 42, 56, and 63 to find the total units of work. Use work = efficiency × time to find the work done by each individual. Calculation: LCM of 42, 56, 63 = 504 units ⇒ Daily work done by A = 504 / 42 = 12 units/day ⇒ Daily work done by B = 504 / 56 = 9 units/day ⇒ Daily work done by C = 504 / 63 = 8 units/day Let's assume the work is completed in D days. ⇒ Total work done by A = 12 × (D - 10) (as A left 10 days before completion) ⇒ Total work done by B = 9 × (D - 12) (as B left 12 days before completion) ⇒ Total work done by C = 8 × D Summing up work done by A, B, and C should be equal to total units of work (504). ⇒ 12(D - 10) + 9(D - 12) + 8D = 504 ⇒ 12D - 120 + 9D - 108 + 8D = 504 ⇒ (12 + 9 + 8)D = 504 + 120 + 108 ⇒ 29D = 732 ⇒ D = 732 / 29 ⇒ D ≈ 25 days Therefore, the work will be completed in approximately 25 days.


Related Questions:

Kiran can do a certain piece of work in 15 days. Kiran and Garima can together do the same work in 10 days, and Kiran, Garima and Mehak can do the same work together in 9 days. In how many days can Kiran and Mehak do the same work?
A and B can do a piece of work in 28 days and 35 days, respectively. They work on alternate days starting with A till the work gets completed. How long (in days) would it take A and B to complete the work?
32 ആളുകൾക്ക് ഒരു ജോലി പൂർത്തിയാക്കുവാൻ 15 ദിവസം വേണമെങ്കിൽ 10 ദിവസം കൊണ്ട് ആ ജോലി പൂർത്തീകരിക്കുവാൻ എത്ര ആളുകൾ വേണം ?
X takes twice as much time as Y or thrice as much time as Z to finish a job. Working together, the trio can finish the job in 2 days. Y alone can do the work in ______.
ഒരു ടാങ്കിലേക്ക് 2 പൈപ്പുകൾ തുറന്നു വച്ചിരിക്കുന്നു. 6 മിനുറ്റുകൊണ്ട് ടാങ്ക് നിറയും. ഒന്നാമത്തെ പൈപ്പ് മാത്രം തുറന്നു വച്ചാൽ 10 മിനിറ്റുകൊണ്ട് നിറയും. എങ്കിൽ രണ്ടാമത്തെ ടാപ്പ് മാത്രംതുറന്നു വച്ചാൽ എത്ര മിനുറ്റുകൊണ്ട് നിറയും ?