Challenger App

No.1 PSC Learning App

1M+ Downloads
A, B, and C can do a piece of work in 42, 56, and 63 days respectively. They started the work together but A left the work 10 days before the completion of the work while B left the work 12 days before the completion. Find the number of days (approximate) to complete the whole work.

A29 days

B25 days

C15 days

D24 days

Answer:

B. 25 days

Read Explanation:

Solution: Given data: Time taken by A to complete the work = 42 days Time taken by B to complete the work = 56 days Time taken by C to complete the work = 63 days A left the work 10 days before completion B left the work 12 days before completion The concept: LCM (Least Common Multiple) and work done concept Find LCM of 42, 56, and 63 to find the total units of work. Use work = efficiency × time to find the work done by each individual. Calculation: LCM of 42, 56, 63 = 504 units ⇒ Daily work done by A = 504 / 42 = 12 units/day ⇒ Daily work done by B = 504 / 56 = 9 units/day ⇒ Daily work done by C = 504 / 63 = 8 units/day Let's assume the work is completed in D days. ⇒ Total work done by A = 12 × (D - 10) (as A left 10 days before completion) ⇒ Total work done by B = 9 × (D - 12) (as B left 12 days before completion) ⇒ Total work done by C = 8 × D Summing up work done by A, B, and C should be equal to total units of work (504). ⇒ 12(D - 10) + 9(D - 12) + 8D = 504 ⇒ 12D - 120 + 9D - 108 + 8D = 504 ⇒ (12 + 9 + 8)D = 504 + 120 + 108 ⇒ 29D = 732 ⇒ D = 732 / 29 ⇒ D ≈ 25 days Therefore, the work will be completed in approximately 25 days.


Related Questions:

A can do a piece of work in 10 days and B in 20 days. They begin together but A leaves 2 days before the completion of the work. The whole work will be done in.
30 men working 5 hours a day can do a task in 16 days. In how many days will 40 men working 6 hours a day do the same task?
ഒരു പരീക്ഷ തുടങ്ങാനായി ഒരു ബെല്ലടിക്കുകയും തുടർന്ന് ഓരോ അരമണിക്കൂർ കഴിയുമ്പോഴും ഓരോ ബെല്ലടിക്കുകയും ചെയ്യുന്നു. ആകെ 6 ബെല്ലടിച്ചുവെങ്കിൽ പരീക്ഷ സമയം എത്ര ?
Two pipes X and Y can fill a cistern in 21 hours and 24 hours, respectively. The pipes are opened simultaneously and it is found that due to a leakage in the bottom it takes 48 minutes more to fill the cistern. When the cistern is full, in how much time will the leak empty it if no pipe is open during that time?
Two pipes A and C can fill a tank in 10 hours and 15 hours respectively. If A is open all the time and C is open for 30 minutes, then find the time needed for the tank to be filled.