App Logo

No.1 PSC Learning App

1M+ Downloads
A, B, and C can do a piece of work in 42, 56, and 63 days respectively. They started the work together but A left the work 10 days before the completion of the work while B left the work 12 days before the completion. Find the number of days (approximate) to complete the whole work.

A29 days

B25 days

C15 days

D24 days

Answer:

B. 25 days

Read Explanation:

Solution: Given data: Time taken by A to complete the work = 42 days Time taken by B to complete the work = 56 days Time taken by C to complete the work = 63 days A left the work 10 days before completion B left the work 12 days before completion The concept: LCM (Least Common Multiple) and work done concept Find LCM of 42, 56, and 63 to find the total units of work. Use work = efficiency × time to find the work done by each individual. Calculation: LCM of 42, 56, 63 = 504 units ⇒ Daily work done by A = 504 / 42 = 12 units/day ⇒ Daily work done by B = 504 / 56 = 9 units/day ⇒ Daily work done by C = 504 / 63 = 8 units/day Let's assume the work is completed in D days. ⇒ Total work done by A = 12 × (D - 10) (as A left 10 days before completion) ⇒ Total work done by B = 9 × (D - 12) (as B left 12 days before completion) ⇒ Total work done by C = 8 × D Summing up work done by A, B, and C should be equal to total units of work (504). ⇒ 12(D - 10) + 9(D - 12) + 8D = 504 ⇒ 12D - 120 + 9D - 108 + 8D = 504 ⇒ (12 + 9 + 8)D = 504 + 120 + 108 ⇒ 29D = 732 ⇒ D = 732 / 29 ⇒ D ≈ 25 days Therefore, the work will be completed in approximately 25 days.


Related Questions:

40 പേർ ഒരു ദിവസം 10 മണിക്കൂർ ജോലി ചെയ്‌താൽ ഒരു ജോലി 12 ദിവസം കൊണ്ട് തീർക്കാൻ ആകും. ഇതേ ജോലി ഒരാൾ ഒരു ദിവസം 11 മണിക്കൂർ ചെയ്‌ത 16 ദിവസം കൊണ്ട് തീർക്കണമെങ്കിൽ എത്ര പേരെ ഒഴിവാക്കണം?
Two pipes P and Q, together can fill a cistern in 20 minutes and P alone can in 30 miutes. Then Q alone can fill the cistern in?
9 men and 12 women can complete a work in 4 days, whereas 3 men and 6 women can complete it in 10 days. The number of days in which 15 women will complete the work is:
C alone can complete a work in 20 days and D alone can complete the same work in 30 days. In how many days C and D together can complete the same work?
Working together, P, Q and R reap a field in 6 days. If P can do it alone in 10 days and Q in 24 days, in how many days will R alone be able to reap the field?