Five men working together can complete a work in 8 days. Om Prakash who can complete the same work independently in 24 days joined them after 4 days. Under the circumstances in how many days the work will be completed?

A5

B4

C7

D3

Answer:

C. 7

Read Explanation:

The total work = 24 (LCM of 8 and 24) The efficiency of five men = 24/8 = 3 The efficiency of Om Prakash = 24/24 = 1 total work done by five men in 4 days = 3 × 4 = 12 Total work need to be completed = 24 - 12 = 12 Total time taken by given men and Om Prakash to complete the remaining work = 12/(3 + 1) = 12/4 = 3 days The total time to complete the work = 4 + 3 = 7 days


Related Questions:

A pipe can fill the tank in 10 minutes and another pipe can empty it in 12 minutes. If both the pipes are opened the time in which the tank is filled
16 workers working 8 hours per day can demolish a building in 32 days. In how many days 24 workers working 12 hours per day can demolish the same building?
ഒരു ക്ളോക്കിൽ 12 അടിക്കാൻ 22 സെക്കന്റ് സമയമെടുക്കും.6 അടിക്കാൻ എത്ര സെക്കന്റ് സമയം വേണം ?
ഒരു ടാങ്കിലേക്ക് 2 പൈപ്പുകൾ തുറന്നു വച്ചിരിക്കുന്നു. 6 മിനുറ്റുകൊണ്ട് ടാങ്ക് നിറയും. ഒന്നാമത്തെ പൈപ്പ് മാത്രം തുറന്നു വച്ചാൽ 10 മിനിറ്റുകൊണ്ട് നിറയും. എങ്കിൽ രണ്ടാമത്തെ ടാപ്പ് മാത്രംതുറന്നു വച്ചാൽ എത്ര മിനുറ്റുകൊണ്ട് നിറയും ?
A യ്ക്ക് 18 ദിവസവും B 20 ദിവസവും C 30 ദിവസവും കൊണ്ട് ഒരു ജോലി പൂർത്തിയാക്കാൻ ക ഴിയും. B യും C യും ചേർന്ന് ജോലി ആരംഭിക്കുകയും 2 ദിവസത്തിന് ശേഷം പോകാൻ നിർബന്ധിതരാവുകയും ചെയ്യുന്നു. ശേഷിക്കുന്ന ജോലി പൂർത്തിയാക്കാൻ A മാത്രം എടുക്കുന്ന സമയം