App Logo

No.1 PSC Learning App

1M+ Downloads
A can do 1/3 of a work in 30 days. B can do 2/5 of the same work in 24 days. They worked together for 20 days. C completed the remaining work in 8 days. Working together A, B and C will complete the same work in:

A15 days

B10 days

C12 days

D18 days

Answer:

C. 12 days

Read Explanation:

Given - A can do 1/3 of a work in 30 days B can do 2/5 of the same work in 24 days C completed remaining work in 8 days. Solution - ⇒ A can do 1/3 of a work in 30 day ⇒ A completed work in 90 days ⇒ B can do 2/5 of the same work in 24 days ⇒ B can completed work in 60 days. ⇒ Let the total work = LCM (90, 60) = 180 unit ⇒ Efficiency of A = 3 unit/day ⇒ Efficiency of B = 2 unit/day ⇒ They both worked for 20 days. work done in 20 days = 20 × 5 = 100 unit ⇒ remaining work = 180 - 100 = 80 unit ⇒ Remaining work done by C in 8 days, ⇒ Efficiency of C = 10 unit/day ⇒ Efficiency of (A + B + C) = 15 unit/day ⇒ Work completed = 180/15 = 12 days ∴ If all worked together, the work completed in 12 days.


Related Questions:

One tap can fill a water tank in 40 minutes and another tap can make the filled tank empty in 60 minutes. If both the taps are open, in how many hours will the empty tank be filled ?
6 പേർ 12 ദിവസം കൊണ്ട് ഒരു ജോലി പൂർത്തിയാക്കുന്നു. എങ്കിൽ 8 പേർ എത്ര ദിവസംകൊണ്ട് ആ ജോലി പൂർത്തീകരിക്കും ?
A fruit vendor restocks apples every 4 days and bananas every 6 days. If he restocks both fruits today, after how many days will he restock both apples and bananas on the same day again?
A can do a piece of work in 5 days, B in 10 days. How long will they take to do it together?
A pipe can filla tankin 30 minutes. Due to a leak in the bottom it is filled in 40 minutes. If the tank is full, how much time will the leak take to empty it?