App Logo

No.1 PSC Learning App

1M+ Downloads
A can do 1/3 of a work in 30 days. B can do 2/5 of the same work in 24 days. They worked together for 20 days. C completed the remaining work in 8 days. Working together A, B and C will complete the same work in:

A15 days

B10 days

C12 days

D18 days

Answer:

C. 12 days

Read Explanation:

Given - A can do 1/3 of a work in 30 days B can do 2/5 of the same work in 24 days C completed remaining work in 8 days. Solution - ⇒ A can do 1/3 of a work in 30 day ⇒ A completed work in 90 days ⇒ B can do 2/5 of the same work in 24 days ⇒ B can completed work in 60 days. ⇒ Let the total work = LCM (90, 60) = 180 unit ⇒ Efficiency of A = 3 unit/day ⇒ Efficiency of B = 2 unit/day ⇒ They both worked for 20 days. work done in 20 days = 20 × 5 = 100 unit ⇒ remaining work = 180 - 100 = 80 unit ⇒ Remaining work done by C in 8 days, ⇒ Efficiency of C = 10 unit/day ⇒ Efficiency of (A + B + C) = 15 unit/day ⇒ Work completed = 180/15 = 12 days ∴ If all worked together, the work completed in 12 days.


Related Questions:

A and B can together complete a task in 18 hours. After 6 hours A leaves. B takes 36 hours to finish rest of the task. How many hours would A have taken to do the task, if he worked alone?
C alone can complete a work in 20 days and D alone can complete the same work in 30 days. In how many days C and D together can complete the same work?
A work could be completed in 22 days. However due to three workers being absent, it was completed in 24 days. The original number of workers was.
A 60 ദിവസം കൊണ്ടും B 40 ദിവസം കൊണ്ടും ഒരു ജോലി ചെയ്യുമെങ്കിൽ രണ്ടുപേരും ചേർന്ന് എത്ര ദിവസം കൊണ്ട് ഈ ജോലി ചെയ്യും?
20 ആളുകൾ 20 ദിവസം കൊണ്ട് ചെയ്തു തീർക്കുന്ന ജോലി ചെയ്യാൻ 10 പേർക്ക് എത്ര ദിവസം വേണം ?