Given -
A can do 1/3
of a work in 30 days
B can do 2/5
of the same work in 24 days
C completed remaining work in 8 days.
Solution -
⇒ A can do 1/3
of a work in 30 day
⇒ A completed work in 90 days
⇒ B can do 2/5
of the same work in 24 days
⇒ B can completed work in 60 days.
⇒ Let the total work = LCM (90, 60) = 180 unit
⇒ Efficiency of A = 3 unit/day
⇒ Efficiency of B = 2 unit/day
⇒ They both worked for 20 days. work done in 20 days = 20 × 5 = 100 unit
⇒ remaining work = 180 - 100 = 80 unit
⇒ Remaining work done by C in 8 days,
⇒ Efficiency of C = 10 unit/day
⇒ Efficiency of (A + B + C) = 15 unit/day
⇒ Work completed = 180/15 = 12 days
∴ If all worked together, the work completed in 12 days.