Challenger App

No.1 PSC Learning App

1M+ Downloads
A can do 1/3 of a work in 30 days. B can do 2/5 of the same work in 24 days. They worked together for 20 days. C completed the remaining work in 8 days. Working together A, B and C will complete the same work in:

A15 days

B10 days

C12 days

D18 days

Answer:

C. 12 days

Read Explanation:

Given - A can do 1/3 of a work in 30 days B can do 2/5 of the same work in 24 days C completed remaining work in 8 days. Solution - ⇒ A can do 1/3 of a work in 30 day ⇒ A completed work in 90 days ⇒ B can do 2/5 of the same work in 24 days ⇒ B can completed work in 60 days. ⇒ Let the total work = LCM (90, 60) = 180 unit ⇒ Efficiency of A = 3 unit/day ⇒ Efficiency of B = 2 unit/day ⇒ They both worked for 20 days. work done in 20 days = 20 × 5 = 100 unit ⇒ remaining work = 180 - 100 = 80 unit ⇒ Remaining work done by C in 8 days, ⇒ Efficiency of C = 10 unit/day ⇒ Efficiency of (A + B + C) = 15 unit/day ⇒ Work completed = 180/15 = 12 days ∴ If all worked together, the work completed in 12 days.


Related Questions:

Every Sunday, Rahul jogs 3 miles. If he jogs 1 mile on Monday and each day he jogs 1 mile more than the previous day. How many miles jogs in 2 weeks:
ഒരു ക്ളോക്കിൽ 12 അടിക്കാൻ 22 സെക്കന്റ് സമയമെടുക്കും.6 അടിക്കാൻ എത്ര സെക്കന്റ് സമയം വേണം ?
6 പൈപ്പുകൾ ഉപയോഗിച്ച് ഒരു ടാങ്കിൽ വെള്ളം നിറയ്ക്കാൻ 1 മണിക്കൂർ 20 മിനിറ്റ് വേണം . എന്നാൽ അഞ്ചു പൈപ്പുകൾ ഉപയോഗിച്ചാണ് നിറയ്ക്കുന്നത് എങ്കിൽ എത്ര സമയം വേണം ?
A can do a piece of work in 10 days. B can do it in 15 days. With the assistance of C, they completed the work in 2 days. C alone can do it in ______________days.
Abhinav, Bikash and Chetan can complete a piece of work in 16 days, 24 days and 32 days respectively. If Bikash leaves 2 days before completion of the work, then find the total days required to complete the work.