Challenger App

No.1 PSC Learning App

★
★
★
★
★
1M+ Downloads
A can do a piece of work in 10 days. B can do it in 15 days. With the assistance of C, they completed the work in 2 days. C alone can do it in ______________days.

A3

B5

C4

D2

Answer:

A. 3

Read Explanation:

3


Related Questions:

A tank is filled in 4 hours by three pipes A, B and C. Pipe C is twice as fast as pipe B and pipe B is twice as fast as pipe A. How much time will pipe A take to fill the tank?
One pipe can fill the tank in 20 min while another pipe can empty it in 60 min. If both the pipes are operated together, how long will it take to fill the tank completely?
4 men and 3 women finish a job in 6 days, and 5 men and 7 women can do the same job in 4 days. How long will 8 men and 6 women take to do the same job?
P and Q can complete a piece of work in 28 days and 35 days, respectively. P begins to do the work and they work alternatively one at a time for one day each. In how many days will the whole work be completed?
The ratio of efficiencies of 2 workers , P and Q is 5:2. If P can complete a project in 12 days, how many days will Q take to complete the same project alone ?