Abhinav, Bikash and Chetan can complete a piece of work in 16 days, 24 days and 32 days respectively. If Bikash leaves 2 days before completion of the work, then find the total days required to complete the work.

A8 days

B9 days

C6 days

D10 days

Answer:

A. 8 days

Read Explanation:

The total unit of work = L.C.M of (16, 24, 32) = 96 The efficiency of Abhinav = 96/16 = 6 The efficiency of Bikash = 96/ 24 = 4 The efficiency of Chetan = 96/ 32 = 3 Let x be the total number of days required to complete the work. 6x + 4(x - 2) + 3x = 96 6x + 4x - 8 + 3x = 96 13x = 96 + 8 13x = 104 x = 8 days


Related Questions:

A certain number of men complete a piece of work in 60 days. If there were 8 men more, the work could be finished in 10 days less. How many men were originally there?
Three pipes A, B, C can empty a tank in 10 hours, 15 hours, 30 hours respectively. If all the three pipes are open simultaneously how much time will the tank be empty.
X, Y and Z can complete a piece of work in 46 days, 92 days and 23 days, respectively. X started the work. Y joined him after 7 days. If Z joined them after 8 days from the beginning, then for how many days did Y work?
Pipes A and B can fill a tank in 18 minutes and 27 minutes, respectively. C is an outlet pipe. When A, B and C are opened together, the empty tank is completely filled in 54 minutes. Pipe C alone can empty the full tank in:
60 ദിവസം കൊണ്ട് ഒരു നിർമ്മാണ ജോലി പൂർത്തിയാക്കാൻ ഒരു കരാറുകാരൻ 210 പേരെ നിയമിച്ചു. 12 ദിവസത്തിന് ശേഷം അദ്ദേഹം 70 പേരെ കൂടി ചേർത്തു. ബാക്കി ജോലികൾ എത്ര ദിവസത്തിനുള്ളിൽ പൂർത്തിയാക്കും?