Challenger App

No.1 PSC Learning App

1M+ Downloads
A can do a piece of work in 32 days and B in 48 days. They work together for 8 days and then A goes away.In how much time (in days) will B finish the 60% of the remaining work?

A18 2/5

B19 3/4

C16 4/5

D17 3/7

Answer:

C. 16 4/5

Read Explanation:

A’s 1 day work (=132)(= \frac{1}{32})
B’s 1 day work (=148)(= \frac{1}{48})

Work done together in 1 day:

132+148=3+296=596\frac{1}{32} + \frac{1}{48} = \frac{3+2}{96} = \frac{5}{96}

Work done in 8 days together:

8×596=4096=5128 \times \frac{5}{96} = \frac{40}{96} = \frac{5}{12}

Remaining work:

1512=7121 - \frac{5}{12} = \frac{7}{12}

60% of the remaining work:

6060% \text{ of } \frac{7}{12} = \frac{3}{5} \times \frac{7}{12} = \frac{7}{20}

Time taken by B alone:

Bs1daywork(=148)B’s 1 day work (= \frac{1}{48})

Time=720148=720×48=33620=16.8\text{Time} = \frac{\frac{7}{20}}{\frac{1}{48}} = \frac{7}{20} \times 48 = \frac{336}{20} = 16.8

Answer: 16.8 days


Related Questions:

A,B,C എന്നീ മൂന്ന് പൈപ്പുകൾക്ക് യഥാക്രമം 10, 15, 30 മണിക്കൂർ കൊണ്ട് ഒരു വാട്ടർ ടാങ്ക് ശൂന്യമാക്കാൻ കഴിയും. മൂന്ന് പൈപ്പുകളും ഒരേസമയം തുറന്നാൽ, ടാങ്ക് ശൂന്യമാക്കാൻ എത്ര സമയം (മണിക്കൂറുകൾ) എടുക്കും?
In what ratio must oil worth Rs. 80/kg is mixed with oil worth Rs. 85/kg and selling the mixture at Rs. 98.25/kg, there can be a profit of 20% ?
നാല് ആളുകൾ ചേർന്ന് ഒരു ജോലി 8 മണിക്കൂർ കൊണ്ട് പൂർത്തിയാക്കും. ജോലി ആരംഭിച്ച് 2 മണിക്കൂർ കഴിഞ്ഞപ്പോൾ രണ്ടുപേർകൂടി അവരോടൊപ്പം ചേർന്നു. ഇനി ജോലി തീർക്കാൻ എത്ര മണിക്കൂർ കൂടി വേണം?
A and B can complete a work in 10 days and 15 days, respectively. They got a total of Rs. 1,250 for that work. What will be B’s share?
Ravi, Manish and Naveen alone can complete a work in 30 days, 15 days and 10 days respectively. They start the work together but Ravi leaves the work after 2 days of the starting of the work and Manish leaves the work after 3 days more. In how many days Naveen will complete the remaining work?