Let the daily work rates of A, B, and C be (a), (b), and (c) respectively.
Step 1: Form equations from the given data
A and B together finish the work in 12 days:
a+b=121
B and C together finish the work in 16 days:
b+c=161
Also, A works for 5 days, B for 7 days, and C for 13 days to complete the whole work:
5a+7b+13c=1
Step 2: Express (a) and (c) in terms of (b)
From the first two equations:
a=121−b
c=161−b
Substitute into the third equation:
5(121−b)
+7b
+13(161−b)=1
125−5b+7b+1613−13b=1
4820+39−11b=1
4859−11b=1
11b=4859−1=4811
b=481
Then
c=161−481
=483−1
=482
=241
Step 3: Find C's time alone
Time taken by C alone=c1=24
24 days
So, C alone can complete the task in 24 days.