Challenger App

No.1 PSC Learning App

1M+ Downloads
A can do a work in 6 days and B in 9 days. How many days will both take together to complete the work?

A7.5 days

B5.4 days

C3.6 days

D3 days

Answer:

C. 3.6 days

Read Explanation:

A's 1 day work = 1/6 B's 1 day work = 1/9 If both work together, their 1 day work, = (1/6)+(1/9) = 5/18 Total days to be taken by both A and B together to complete the work = 18/5 days = 3.6 days.


Related Questions:

ഒരു തീവണ്ടി ഒരു ടെലഗ്രാഫ് പോസ്റ്റ് 8 സെക്കൻഡ് കൊണ്ടും 105 മീറ്റർ നീളമുള്ള പാലം 20 സെകണ്ട് കൊണ്ടും കടന്നുപോകുന്നു. തീവണ്ടിയുടെ നീളം എത്ര ?
P is twice as efficient as Q. Q takes 12 days to complete a job. If both of them work together, how much time will they take to complete the job?
There are 3 taps, A, B and C, in a tank. These can fill the tank in 10 h, 20 h and 25 h, respectively. At first, all three taps are opened simultaneously. After 2 h, tap C is closed and tap A and B keep running. After 4 h, tap B is also closed. The remaining tank is filled by tap A alone. Find the percentage of work done by tap A itself.
A and B together can complete a work in 30 day. They started together but after 6 days A left the work and the work is completed by B after 36 more days. A alone can complete the entire work in how many days?
രാജുവും ടോമും ചേർന്ന് 10 ദിവസം കൊണ്ട് ഒരു ജോലി പൂർത്തിയാക്കും. ടോമും അപ്പുവും ചേർന്ന് 12 ദിവസത്തിനുള്ളിൽ ജോലി ചെയ്യാൻ കഴിയും. അപ്പുവും രാജുവും ചേർന്ന് 15 ദിവസം കൊണ്ട് ജോലി പൂർത്തിയാക്കും. മൂന്നുപേരും ഒരുമിച്ച് പ്രവർത്തിച്ചാൽ എത്ര ദിവസം കൊണ്ട് അവർ ജോലി പൂർത്തിയാക്കും?