Let's calculate their combined work rate.
Step 1: Individual work rates
Step 2: Combined rate
81+121
=243+242
=245
Together, they complete (245)of the work per day.
Step 3: Work done in 3 days
3×245
=2415
=85
Step 4: Work left
1−85
=83
Answer:(83) of the work is left.