A can finish 3/5th of a task in 6 days and B can finish 2/3th of the same task in 12 days. A and B worked together for 5 days. C alone completed the remaining task in 8 days. B and C, working together, will complete the same task in:

A10

B18

C12

D15

Answer:

C. 12

Read Explanation:

Solution: Given: A can finish 35/ of a task = 6 days B can finish 2/3 of the same task = 12 days A and B worked together = 5 days C alone completed the remaining task = 8 days Concept Used: If a man can do a work in t days then in 1 day he will do 1/t part of the work Calculation: A alone can finish task = 6 × (5/3) ⇒ 10 days B alone can finish task = 12 × (3/2) ⇒18 days ⇒ A and B worked for 5 days = (5/10) + (5/18) ⇒ (45 + 25) /90 = 70/90 ⇒ 7/9 ⇒ Remaining work = 1 - (7/9) ⇒ 20/90 = 2/9 2/9th of work completed by C = 8 days C alone can finish task = 8 × (9/2) = 36 days ⇒ B + C working together can do in 1 day = 1/18 + 1/36 ⇒ (2 + 1)/36 = 3/36 = 1/12 In one day B and C together can complete = 1/12 of the task B and C together can complete a task = 12 day ∴ The number of days taken to complete a task B and C together is 12


Related Questions:

Abhay and Bharat can complete a certain piece of work in 9 and 11 days, respectively, They started to work together, and after 3 days, Bharat left. In how many days will Abhay complete the remaining work?
A and B together take 5 days to do work, B and C take 7 days to do the same, and A and C take 4 days to do it. Who among these will take the least time to do it alone?
Thirty men take 20 days to complete a job working 9 hours a day. How many hour a day should 40 men take in 20 days to complete the job?
15 men finish a job in 21 days by working 8 hour a day. If 3 women work equal to 2 men, then how many days will 21 women take to complete the work by working 6 hours/day?
മനുവിന് ഒരു ജോലി ചെയ്യാൻ 10 ദിവസം വേണം അനുവിന് അത് ചെയ്ത് തീർക്കാൻ 15 ദിവസം വേണം. എങ്കിൽ രണ്ടു പേരും ചേർന്ന് ഈ ജോലി എത്ര ദിവസം കൊണ്ട് ചെയ്തു തീർക്കും?