1 man’s work = (201)
1 woman’s work =(301)
1 boy’s work =(501)
Work done by women (every day)
6 women=6×301=51
Work on alternate days (men + boys + women)
2 men + 5 boys work only on alternate days.
2×201=101
5×501=101
Men + boys work =101+101=51
Total work on working day:
51(women)+51(men+boys)=52
Work on non-alternate days (only women)
51
Work done in 2 days
52+51=53
Work completed in 4 days
2×53=56
But full work = 1, so work finishes during the 4th day.
Work done in 3 days:
53+52=1
But this ends on a working day, so we must calculate fraction properly.
Exact time
Work in 3 days:
53+51+52=56
So excess work in 3 days:
51
Work rate on working day = ( \frac{2}{5} )
Time required to finish remaining:
5251=21
Correct sequencing gives total time:
331 days