A work could be completed in 22 days. However due to three workers being absent, it was completed in 24 days. The original number of workers was.

A33

B18

C36

D25

Answer:

C. 36

Read Explanation:

let the original number of workers be x then x * 22 = (x-3) * 24 22x = 24x -72 24x - 22x = 72 2x = 72, x=36 No of original workers = 36


Related Questions:

P can do a piece of work in 48 days, which Q can do in 18 days. Q worked at it for 15 days. P can finish the remaining work in:
Two pipes can fill a cistern separately in 10 hours and 15 hours. They can together fill the cistern in
Ravi, Manish and Naveen alone can complete a work in 30 days, 15 days and 10 days respectively. They start the work together but Ravi leaves the work after 2 days of the starting of the work and Manish leaves the work after 3 days more. In how many days Naveen will complete the remaining work?
A - യ്ക്ക് ഒരു ജോലി ചെയ്യാൻ 35 ദിവസവും, B-യ്ക്ക് അതേ ജോലി ചെയ്യാൻ 45 ദിവസവും ആവശ്യമാണ്. A - യും B - യും കൂടി ആ ജോലി 7 ദിവസം ചെയ് തു. അതിനുശേഷം A പോയാൽ ബാക്കി ജോലി B ഒറ്റയ്ക്ക് എത്ര ദിവസം കൊണ്ട് പൂർത്തിയാക്കും?
ഒരു പ്രത്യേക ജോലി 2 പുരുഷന്മാർക്ക് 10 ദിവസം കൊണ്ടും 5 സ്ത്രീകൾക്ക് 8 ദിവസം കൊണ്ടുംപൂർത്തിയാക്കാൻ കഴിയും. എങ്കിൽ 1 പുരുഷനും 2 സ്ത്രീകളും ചേർന്ന് പ്രസ്തുത ജോലി എത്ര ദിവസംകൊണ്ട് പൂർത്തിയാക്കാൻ കഴിയും ?