A work could be completed in 22 days. However due to three workers being absent, it was completed in 24 days. The original number of workers was.

A33

B18

C36

D25

Answer:

C. 36

Read Explanation:

let the original number of workers be x then x * 22 = (x-3) * 24 22x = 24x -72 24x - 22x = 72 2x = 72, x=36 No of original workers = 36


Related Questions:

രാജു ഒരു ജോലി 20 ദിവസം കൊണ്ട് ചെയ്ത് തീർക്കും. ഗോപു അതേ ജോലി ചെയ്യാൻ 30 ദിവസം എടുക്കും. എങ്കിൽ രണ്ടുപേരും ചേർന്നാൽ ആ ജോലി എത്ര ദിവസം കൊണ്ട് ചെയ്തു തീർക്കും ?
There are sufficient food for 500 men for 45 days. After 36 days, 200 men left the place. For how many days will the rest of the food last for the remaining people?
Tap A can fill a tank in 6 hours and tap B can empty the same tank in 10 hours. If both taps are opened together, then how much time (in hours) will be taken to fill the tank?
A tap can fill a tank in 48 minutes, where as another tap can empty it in 2 hours. If both the taps are opened at 11:40 am then the tank will be filled at
60 ദിവസം കൊണ്ട് ഒരു നിർമ്മാണ ജോലി പൂർത്തിയാക്കാൻ ഒരു കരാറുകാരൻ 210 പേരെ നിയമിച്ചു. 12 ദിവസത്തിന് ശേഷം അദ്ദേഹം 70 പേരെ കൂടി ചേർത്തു. ബാക്കി ജോലികൾ എത്ര ദിവസത്തിനുള്ളിൽ പൂർത്തിയാക്കും?