According to the principle of continuity in coordination:

ACoordination should start only at year-end

BIt should be a regular, ongoing process

CIt should be handled by external consultants

DIt is only required during planning

Answer:

B. It should be a regular, ongoing process

Read Explanation:

  • The principle of continuity means coordination should run throughout the organisational workflow, not as a one-time activity.


Related Questions:

Consider the following statements regarding Planning in management:

  1. Planning is always a one-time activity designed for a fixed time frame and does not require revision once implemented.
  2. Planning has primacy over other managerial functions as it lays the foundation for organising, staffing, directing and controlling.
  3. Luther Gullick’s acronym POSDCORB includes ‘Controlling’ as its last function.
  4. According to Henry Fayol’s POCCC, ‘Commanding’ is a function distinct from ‘Directing’.
    In controlling, comparing actual performance with standards helps in:
    What is the purpose of "follow up/appraisal of plans" in the planning process?
    Which of the following is a key feature of planning?
    What is the fundamental difference in approach between "recruitment" and "selection"