A and B can do a piece of work in 28 days and 35 days, respectively. They work on alternate days starting with A till the work gets completed. How long (in days) would it take A and B to complete the work?

A311531\frac15

B311231\frac12

C3131

D311931\frac19

Answer:

3131

Read Explanation:

A can do the work in =28=28

B can do the work in =35=35

LCM of this two is the total work = 140

efficiency of A =140/28=5= 140/28=5

efficiency of B =140/35=4= 140/35=4

straiting A alternate with B the two day work is = 9

140/9=15140/9=15 and reminder 5

days =15×2=30=15\times 2=30

one day work is done by A

30+1=3130+1=31


Related Questions:

A ഒരു ജോലി 2 ദിവസം കൊണ്ടും B 3 ദിവസം കൊണ്ടും C അത് 6 ദിവസം കൊണ്ടും ചെയ്തീർക്കും. എങ്കിൽ അവർ മൂന്നു പേരും കൂടി ആ ജോലി എത്ര ദിവസം കൊണ്ട് ചെയ്ത തീർക്കും ?
A can make a divider in 20 days, while B can make it in 50 days. If they work together and get Rs.3500, then find the share of B in the amount.
15 ആളുകൾ ചേർന്ന് ഒരു ജോലി 18 ദിവസം കൊണ്ട് തീർക്കും. എന്നാൽ അതേ ജോലി 10 ആളുകൾ എത്ര ദിവസം കൊണ്ട് തീർക്കും ?
40 persons can repair a bridge in 12 days. If 8 more persons join them, then in how many days bridge can be repaired?
The efficiency of A and B to do a work is in the ratio 3 ∶ 5. Working together they can complete a work in 30 days. In how many days A alone will complete that work?