A and B can do a work in 15 days and 10 days respectively. They begin the work together but B leaves after two days. Now A completes the remaining work. The total number of days needed for the completion of the work is:

A15 days

B18 days

C12 days

D10 days

Answer:

C. 12 days

Read Explanation:

Solution: Given: A can-do work in 15 days B can do work in 10 days Concept used: A can do a work in n days So, A's one day work = 1/n Calculation: A can-do a work in 15 days ⇒ A's one-day work = 1/15 B can do a work in 10 days ⇒ B's one day work = 1/10 A and B's one day work = 1/15 + 1/10 ⇒ 5/30 = 1/6 Two days work of A and B will be 2/6 = 1/3 Remaining work after B left = 1- 1/3 = 2/3 A will finished remaining work in = (2/3) × 15 = 10 days ∴ Total number of days to complete work is 10 + 2 = 12 days Shortcut Trick LCM of 15 and 10 is 30 A = 15 × 2 = 30 B = 10 × 3 = 30 Total work = 30 unit B does 3 unit work in one day A does 2 unit work in one day ⇒ (A + B)'s one day's work is (3 + 2) unit = 5 unit ⇒ (A + B)'s two days' work is (5 × 2) unit = 10 unit ⇒ Remaining work = 30 - 10 = 20 unit A will complete remaining work in, 20/2 = 10 days Total number of days = (10 + 2) days = 12 days ∴ Total number of days to complete work is 12 days


Related Questions:

A and B undertake to complete a piece of work for ₹600. A alone can complete it in 4 days while B alone can complete it in 6 days. With the help of C, they finish the work in 2 days. Find the share of C in the payment received.
40 persons can repair a bridge in 12 days. If 8 more persons join them, then in how many days bridge can be repaired?
Two pipes A and B can fill a tank in 24 minutes and 32 minutes respectively. If both the pipes are opened simultaneously, after how much time should A be closed so that the tank is full in 20 minutes?
മനു മിഹിറിൻ്റെ ഇരട്ടി വേഗത്തിൽ പ്രവർത്തിക്കുന്നു. ഇരുവരും ചേർന്ന് 12 ദിവസം കൊണ്ട് ഒരു ജോലി പൂർത്തിയാക്കിയാൽ മനു മാത്രം ജോലി പൂർത്തിയാക്കാൻ എടുക്കുന്ന സമയം
40 പേർ ഒരു ദിവസം 10 മണിക്കൂർ ജോലി ചെയ്‌താൽ ഒരു ജോലി 12 ദിവസം കൊണ്ട് തീർക്കാൻ ആകും. ഇതേ ജോലി ഒരാൾ ഒരു ദിവസം 11 മണിക്കൂർ ചെയ്‌ത 16 ദിവസം കൊണ്ട് തീർക്കണമെങ്കിൽ എത്ര പേരെ ഒഴിവാക്കണം?