Working 7 hours a day, 18 persons can complete a certain work in 32 days. In how many days would 14 persons complete the same work, working 8 hours a day?

A42

B30

C36

D28

Answer:

C. 36

Read Explanation:

M1 × D1 × T1 = M2 × D2 × T2 18 × 32 × 7 = 14 × D2 × 8 D2 = (18 × 32 × 7)/14 × 8 D2 = 36


Related Questions:

30 men working 5 hours a day can do a task in 16 days. In how many days will 40 men working 6 hours a day do the same task?
If 45 persons can complete a work in 18 days, working 8 hours a day, then how many persons are required to complete two-thirds of the same work in 20 days, working 9 hours a day?
In a race, an athlete covers a distance of 360 m in 60 sec in the first lap. He covers the second lap of the same length in 180 sec. What is the average speed (in m/sec) of the athlete?
12 ആളുകൾ 25 ദിവസംകൊണ്ട് ചെയ്തുതീർക്കുന്ന ജോലി 15 ദിവസംകൊണ്ട് തീർക്കാൻ ഇനി എത ആളുകൾ കൂടി വേണം?
Abhay and Bharat can complete a certain piece of work in 17 and 10 days, respectively, They started to work together, and after 3 days, Bharat left. In how many days will Abhay complete the remaining work?