App Logo

No.1 PSC Learning App

1M+ Downloads
Sankar and Vishnu work alternately in a tailoring shop on an order of stitching 21 suits. Sankar starts the work, stitches 3 suits in two days, and takes a break, during which Vishnu stitches 3 suits in three days, and then takes a break. This pattern is repeated till all the 21 suits are stitched. How many days did it take the duo to complete the work?

A18 days

B15 days

C17 days

D16 days

Answer:

C. 17 days

Read Explanation:

image.png

Related Questions:

A can do 331333\frac{1}{3}% of a work in 10 days and B can do 662366\frac{2}{3}% of the same work in 8 days. Both together worked for 8 days then C alone completes the remaining work in 3 days. A and C together will complete 56\frac{5}{6} part of the original work in:

If 4 x 1 = 17, 1 x 3 =4. Then 5x6 =
A and B can together complete a task in 18 hours. After 6 hours A leaves. B takes 36 hours to finish rest of the task. How many hours would A have taken to do the task, if he worked alone?
A is twice as good as a workman as B. And together, they finish a piece of work in 20 days. In how many days, will A alone finish the work?
A and B working separately can finish a work in 15 days and 20 days. respectively. If they work on alternate days. A starting first, and if the work goes on for 8 days, what part of the work will be left unfinished?